Time and Work

Time and Work problems involve calculating the time required for one or more persons to complete a task, given their individual work rates. These problems test your understanding of work rate (work per unit time) and the inverse relationship between time and rate.

10Worksheets
200+Practice Questions
IntermediateDifficulty
3-4 hoursHours to Master

Introduction to Time and Work

Time and Work problems involve calculating the time required for one or more persons to complete a task, given their individual work rates. These problems test your understanding of work rate (work per unit time) and the inverse relationship between time and rate.

Prerequisites

Work rate concept (work/time) Fraction addition/subtraction LCM method Inverse proportionality
Why This Matters: Time and Work problems appear in 2-3 questions in SSC CGL, Banking PO, and Railways exams. They are a staple of quantitative aptitude.

How to Solve Time and Work Problems

1

Step 1: Let total work = LCM of given times (or 1 unit)

2

Step 2: Calculate individual work rates: Rate = Total work / Time

3

Step 3: For combined work: Combined rate = Sum of individual rates

4

Step 4: Time together = Total work / Combined rate

5

Step 5: For 'n days alone then together' problems, calculate work done and remaining

6

Step 6: For efficiency problems, express rates in terms of efficiency

7

Step 7: Verify that answer is less than individual times

Pro Strategy: Use the LCM method to avoid fractions. Assume total work = LCM of all individual times. This gives integer work rates for easier calculation.

Example Problem

Example: A can complete a work in 10 days, B in 15 days. How many days will they take together? Solution: Step 1: Let total work = LCM(10,15) = 30 units Step 2: A's rate = 30/10 = 3 units/day, B's rate = 30/15 = 2 units/day Step 3: Combined rate = 3 + 2 = 5 units/day Step 4: Time together = 30/5 = 6 days Answer: 6 days Shortcut: 1/10 + 1/15 = (3+2)/30 = 5/30 = 1/6 → 6 days

Pro Tips & Tricks

  • If A takes a days, B takes b days, together = (a×b)/(a+b) days
  • If A is p% more efficient than B, then A's rate = B's rate × (1 + p/100)
  • If A and B together take t days, and A alone takes a days, then B alone = (a×t)/(a-t)
  • Work done = Rate × Time
  • Remaining work = 1 - Work done (when total work = 1)
  • Use unitary method: 1 day's work = 1/Time

Shortcut Methods to Solve Faster

Together time = (a×b)/(a+b) for two persons
For three persons: 1/T = 1/a + 1/b + 1/c
If A takes a days, B takes b days, C takes c days, together = (abc)/(ab+bc+ca)

Common Mistakes to Avoid

Adding times instead of rates
Forgetting to take reciprocal when using 1-day work method
Assuming work rates are additive (they are, but times are not)
Not converting efficiency to rates correctly

Exam Importance

Time and Work is an important topic for various competitive exams. Here's how frequently it appears:

SSC CGL
2-3 questions
BANKING PO
2-3 questions
RAILWAYS RRB
2-3 questions
CAT
1-2 questions
INSURANCE
2-3 questions

Ready to Master Time and Work?

Start with Worksheet 1 and work your way up to expert level! Each worksheet includes:

20 practice questions
Detailed solutions
Step-by-step explanations
Start Practicing Now