Time and Work - Expert Level: conceptual clarity Time and Work EXPERT

This skill evaluation ⚡ worksheet focuses on Time and Work - a key topic in Arithmetic Problems. You'll solve 20 expert-level problems (Worksheet 9 of 10). The primary focus is on conceptual clarity. Master time and work ssc cgl, time and work reasoning tricks, and fast time and work solving through systematic practice.

📝 Worksheet 9 of 10 • 20 questions • ⏱️ Estimated time: 20 minutes • 🎯 Expert level

What you'll learn in this worksheet:
Your progress through Time and Work
Worksheet 9 of 10 (88% complete)

Question 1

If A can complete a work in 4 days, and B in 9 days, how long will they take together?
Time = (A * B) / (A + B) = (4*9)/(4+9) = 2.77 days.

Question 2

If A can complete a work in 2 days, and B in 6 days, how long will they take together?
Time = (A * B) / (A + B) = (2*6)/(2+6) = 1.5 days.

Question 3

If A can complete a work in 5 days, and B in 12 days, how long will they take together?
Time = (A * B) / (A + B) = (5*12)/(5+12) = 3.53 days.

Question 4

If A can complete a work in 5 days, and B in 11 days, how long will they take together?
Time = (A * B) / (A + B) = (5*11)/(5+11) = 3.44 days.

Question 5

If A can complete a work in 4 days, and B in 8 days, how long will they take together?
Time = (A * B) / (A + B) = (4*8)/(4+8) = 2.67 days.

Question 6

If A can complete a work in 5 days, and B in 8 days, how long will they take together?
Time = (A * B) / (A + B) = (5*8)/(5+8) = 3.08 days.

Question 7

If A can complete a work in 5 days, and B in 8 days, how long will they take together?
Time = (A * B) / (A + B) = (5*8)/(5+8) = 3.08 days.

Question 8

If A can complete a work in 2 days, and B in 11 days, how long will they take together?
Time = (A * B) / (A + B) = (2*11)/(2+11) = 1.69 days.

Question 9

If A can complete a work in 3 days, and B in 7 days, how long will they take together?
Time = (A * B) / (A + B) = (3*7)/(3+7) = 2.1 days.

Question 10

If A can complete a work in 5 days, and B in 7 days, how long will they take together?
Time = (A * B) / (A + B) = (5*7)/(5+7) = 2.92 days.

Question 11

If A can complete a work in 3 days, and B in 11 days, how long will they take together?
Time = (A * B) / (A + B) = (3*11)/(3+11) = 2.36 days.

Question 12

If A can complete a work in 5 days, and B in 8 days, how long will they take together?
Time = (A * B) / (A + B) = (5*8)/(5+8) = 3.08 days.

Question 13

If A can complete a work in 5 days, and B in 8 days, how long will they take together?
Time = (A * B) / (A + B) = (5*8)/(5+8) = 3.08 days.

Question 14

If A can complete a work in 2 days, and B in 8 days, how long will they take together?
Time = (A * B) / (A + B) = (2*8)/(2+8) = 1.6 days.

Question 15

If A can complete a work in 5 days, and B in 7 days, how long will they take together?
Time = (A * B) / (A + B) = (5*7)/(5+7) = 2.92 days.

Question 16

If A can complete a work in 2 days, and B in 9 days, how long will they take together?
Time = (A * B) / (A + B) = (2*9)/(2+9) = 1.64 days.

Question 17

If A can complete a work in 4 days, and B in 6 days, how long will they take together?
Time = (A * B) / (A + B) = (4*6)/(4+6) = 2.4 days.

Question 18

If A can complete a work in 3 days, and B in 7 days, how long will they take together?
Time = (A * B) / (A + B) = (3*7)/(3+7) = 2.1 days.

Question 19

If A can complete a work in 2 days, and B in 6 days, how long will they take together?
Time = (A * B) / (A + B) = (2*6)/(2+6) = 1.5 days.

Question 20

If A can complete a work in 5 days, and B in 7 days, how long will they take together?
Time = (A * B) / (A + B) = (5*7)/(5+7) = 2.92 days.
Previous Worksheet Next Worksheet