Time and Work: Worksheet 6 - Intermediate-Advanced Practice Time and Work INTERMEDIATE ADVANCED

Ready to master Time and Work? This timed practice ⚡ worksheet (6/10) presents 20 intermediate-advanced-level challenges. Focus area: speed building. Learn to solve time and work tricks, handle time and work shortcut methods, and perfect time and work bank exam questions with our step-by-step solutions.

📝 Worksheet 6 of 10 • 20 questions • ⏱️ Estimated time: 20 minutes • 🎯 Intermediate Advanced level

What you'll learn in this worksheet:
Your progress through Time and Work
Worksheet 6 of 10 (55% complete)

Question 1

If A can complete a work in 2 days, and B in 6 days, how long will they take together?
Time = (A * B) / (A + B) = (2*6)/(2+6) = 1.5 days.

Question 2

If A can complete a work in 3 days, and B in 6 days, how long will they take together?
Time = (A * B) / (A + B) = (3*6)/(3+6) = 2.0 days.

Question 3

If A can complete a work in 4 days, and B in 11 days, how long will they take together?
Time = (A * B) / (A + B) = (4*11)/(4+11) = 2.93 days.

Question 4

If A can complete a work in 3 days, and B in 6 days, how long will they take together?
Time = (A * B) / (A + B) = (3*6)/(3+6) = 2.0 days.

Question 5

If A can complete a work in 2 days, and B in 6 days, how long will they take together?
Time = (A * B) / (A + B) = (2*6)/(2+6) = 1.5 days.

Question 6

If A can complete a work in 2 days, and B in 11 days, how long will they take together?
Time = (A * B) / (A + B) = (2*11)/(2+11) = 1.69 days.

Question 7

If A can complete a work in 5 days, and B in 11 days, how long will they take together?
Time = (A * B) / (A + B) = (5*11)/(5+11) = 3.44 days.

Question 8

If A can complete a work in 4 days, and B in 7 days, how long will they take together?
Time = (A * B) / (A + B) = (4*7)/(4+7) = 2.55 days.

Question 9

If A can complete a work in 5 days, and B in 12 days, how long will they take together?
Time = (A * B) / (A + B) = (5*12)/(5+12) = 3.53 days.

Question 10

If A can complete a work in 4 days, and B in 7 days, how long will they take together?
Time = (A * B) / (A + B) = (4*7)/(4+7) = 2.55 days.

Question 11

If A can complete a work in 4 days, and B in 6 days, how long will they take together?
Time = (A * B) / (A + B) = (4*6)/(4+6) = 2.4 days.

Question 12

If A can complete a work in 2 days, and B in 11 days, how long will they take together?
Time = (A * B) / (A + B) = (2*11)/(2+11) = 1.69 days.

Question 13

If A can complete a work in 4 days, and B in 11 days, how long will they take together?
Time = (A * B) / (A + B) = (4*11)/(4+11) = 2.93 days.

Question 14

If A can complete a work in 3 days, and B in 11 days, how long will they take together?
Time = (A * B) / (A + B) = (3*11)/(3+11) = 2.36 days.

Question 15

If A can complete a work in 4 days, and B in 10 days, how long will they take together?
Time = (A * B) / (A + B) = (4*10)/(4+10) = 2.86 days.

Question 16

If A can complete a work in 4 days, and B in 11 days, how long will they take together?
Time = (A * B) / (A + B) = (4*11)/(4+11) = 2.93 days.

Question 17

If A can complete a work in 5 days, and B in 9 days, how long will they take together?
Time = (A * B) / (A + B) = (5*9)/(5+9) = 3.21 days.

Question 18

If A can complete a work in 5 days, and B in 7 days, how long will they take together?
Time = (A * B) / (A + B) = (5*7)/(5+7) = 2.92 days.

Question 19

If A can complete a work in 4 days, and B in 9 days, how long will they take together?
Time = (A * B) / (A + B) = (4*9)/(4+9) = 2.77 days.

Question 20

If A can complete a work in 4 days, and B in 12 days, how long will they take together?
Time = (A * B) / (A + B) = (4*12)/(4+12) = 3.0 days.