Project Task Dependency Beginner-Intermediate Worksheet: Focus on common variations practice Project Task Dependency BEGINNER INTERMEDIATE

Level up your Project Task Dependency skills! You're at Worksheet 4 of 10 (33% through this series). This step-up challenge worksheet features 20 beginner-intermediate-level problems with a focus on common variations practice. Topics covered: project task dependency for competitive exams, how to solve project task dependency, project task dependency tricks.

📝 Worksheet 4 of 10 • 20 questions • ⏱️ Estimated time: 20 minutes • 🎯 Beginner Intermediate level

What you'll learn in this worksheet:
Your progress through Project Task Dependency
Worksheet 4 of 10 (33% complete)

Question 1

A project consists of the following tasks: - Task A (Requirements Analysis): 2 days, Depends on: None - Task B (Design): 3 days, Depends on: A - Task C (Database Setup): 2 days, Depends on: A - Task D (Development): 5 days, Depends on: B, C - Task E (Testing): 3 days, Depends on: D What is the minimum number of days required to complete the entire project?
Step-by-step solution:

Critical Path Method (CPM):
1. Identify dependencies and calculate earliest start times:
- Task A: Starts on Day 0, Duration 2 days
Finishes on Day 2
- Task B: Starts on Day 2, Duration 3 days
Finishes on Day 5
- Task C: Starts on Day 2, Duration 2 days
Finishes on Day 4
- Task D: Starts on Day 5, Duration 5 days
Finishes on Day 10
- Task E: Starts on Day 10, Duration 3 days
Finishes on Day 13

2. Task timeline:
Task A: Days 0-2
Task B: Days 2-5 (after A)
Task C: Days 2-4 (after A)
Task D: Days 5-10 (after B and C)
Task E: Days 10-13 (after D)

3. Critical path: A -> B -> D -> E (or A -> C -> D -> E)
4. Total project duration: 13 days

Key Strategy: Calculate earliest start time for each task based on predecessor completion times; the longest path determines total duration.

Question 2

A project consists of the following tasks: - Task A (Requirements Analysis): 2 days, Depends on: None - Task B (Design): 3 days, Depends on: A - Task C (Database Setup): 2 days, Depends on: A - Task D (Development): 5 days, Depends on: B, C - Task E (Testing): 3 days, Depends on: D What is the minimum number of days required to complete the entire project?
Step-by-step solution:

Critical Path Method (CPM):
1. Identify dependencies and calculate earliest start times:
- Task A: Starts on Day 0, Duration 2 days
Finishes on Day 2
- Task B: Starts on Day 2, Duration 3 days
Finishes on Day 5
- Task C: Starts on Day 2, Duration 2 days
Finishes on Day 4
- Task D: Starts on Day 5, Duration 5 days
Finishes on Day 10
- Task E: Starts on Day 10, Duration 3 days
Finishes on Day 13

2. Task timeline:
Task A: Days 0-2
Task B: Days 2-5 (after A)
Task C: Days 2-4 (after A)
Task D: Days 5-10 (after B and C)
Task E: Days 10-13 (after D)

3. Critical path: A -> B -> D -> E (or A -> C -> D -> E)
4. Total project duration: 13 days

Key Strategy: Calculate earliest start time for each task based on predecessor completion times; the longest path determines total duration.

Question 3

A project consists of the following tasks: - Task A (Requirements Analysis): 2 days, Depends on: None - Task B (Design): 3 days, Depends on: A - Task C (Database Setup): 2 days, Depends on: A - Task D (Development): 5 days, Depends on: B, C - Task E (Testing): 3 days, Depends on: D What is the minimum number of days required to complete the entire project?
Step-by-step solution:

Critical Path Method (CPM):
1. Identify dependencies and calculate earliest start times:
- Task A: Starts on Day 0, Duration 2 days
Finishes on Day 2
- Task B: Starts on Day 2, Duration 3 days
Finishes on Day 5
- Task C: Starts on Day 2, Duration 2 days
Finishes on Day 4
- Task D: Starts on Day 5, Duration 5 days
Finishes on Day 10
- Task E: Starts on Day 10, Duration 3 days
Finishes on Day 13

2. Task timeline:
Task A: Days 0-2
Task B: Days 2-5 (after A)
Task C: Days 2-4 (after A)
Task D: Days 5-10 (after B and C)
Task E: Days 10-13 (after D)

3. Critical path: A -> B -> D -> E (or A -> C -> D -> E)
4. Total project duration: 13 days

Key Strategy: Calculate earliest start time for each task based on predecessor completion times; the longest path determines total duration.

Question 4

A project consists of the following tasks: - Task A (Requirements Analysis): 2 days, Depends on: None - Task B (Design): 3 days, Depends on: A - Task C (Database Setup): 2 days, Depends on: A - Task D (Development): 5 days, Depends on: B, C - Task E (Testing): 3 days, Depends on: D What is the minimum number of days required to complete the entire project?
Step-by-step solution:

Critical Path Method (CPM):
1. Identify dependencies and calculate earliest start times:
- Task A: Starts on Day 0, Duration 2 days
Finishes on Day 2
- Task B: Starts on Day 2, Duration 3 days
Finishes on Day 5
- Task C: Starts on Day 2, Duration 2 days
Finishes on Day 4
- Task D: Starts on Day 5, Duration 5 days
Finishes on Day 10
- Task E: Starts on Day 10, Duration 3 days
Finishes on Day 13

2. Task timeline:
Task A: Days 0-2
Task B: Days 2-5 (after A)
Task C: Days 2-4 (after A)
Task D: Days 5-10 (after B and C)
Task E: Days 10-13 (after D)

3. Critical path: A -> B -> D -> E (or A -> C -> D -> E)
4. Total project duration: 13 days

Key Strategy: Calculate earliest start time for each task based on predecessor completion times; the longest path determines total duration.

Question 5

A project consists of the following tasks: - Task A (Requirements Analysis): 2 days, Depends on: None - Task B (Design): 3 days, Depends on: A - Task C (Database Setup): 2 days, Depends on: A - Task D (Development): 5 days, Depends on: B, C - Task E (Testing): 3 days, Depends on: D What is the minimum number of days required to complete the entire project?
Step-by-step solution:

Critical Path Method (CPM):
1. Identify dependencies and calculate earliest start times:
- Task A: Starts on Day 0, Duration 2 days
Finishes on Day 2
- Task B: Starts on Day 2, Duration 3 days
Finishes on Day 5
- Task C: Starts on Day 2, Duration 2 days
Finishes on Day 4
- Task D: Starts on Day 5, Duration 5 days
Finishes on Day 10
- Task E: Starts on Day 10, Duration 3 days
Finishes on Day 13

2. Task timeline:
Task A: Days 0-2
Task B: Days 2-5 (after A)
Task C: Days 2-4 (after A)
Task D: Days 5-10 (after B and C)
Task E: Days 10-13 (after D)

3. Critical path: A -> B -> D -> E (or A -> C -> D -> E)
4. Total project duration: 13 days

Key Strategy: Calculate earliest start time for each task based on predecessor completion times; the longest path determines total duration.

Question 6

A project consists of the following tasks: - Task A (Requirements Analysis): 2 days, Depends on: None - Task B (Design): 3 days, Depends on: A - Task C (Database Setup): 2 days, Depends on: A - Task D (Development): 5 days, Depends on: B, C - Task E (Testing): 3 days, Depends on: D What is the minimum number of days required to complete the entire project?
Step-by-step solution:

Critical Path Method (CPM):
1. Identify dependencies and calculate earliest start times:
- Task A: Starts on Day 0, Duration 2 days
Finishes on Day 2
- Task B: Starts on Day 2, Duration 3 days
Finishes on Day 5
- Task C: Starts on Day 2, Duration 2 days
Finishes on Day 4
- Task D: Starts on Day 5, Duration 5 days
Finishes on Day 10
- Task E: Starts on Day 10, Duration 3 days
Finishes on Day 13

2. Task timeline:
Task A: Days 0-2
Task B: Days 2-5 (after A)
Task C: Days 2-4 (after A)
Task D: Days 5-10 (after B and C)
Task E: Days 10-13 (after D)

3. Critical path: A -> B -> D -> E (or A -> C -> D -> E)
4. Total project duration: 13 days

Key Strategy: Calculate earliest start time for each task based on predecessor completion times; the longest path determines total duration.

Question 7

A project consists of the following tasks: - Task A (Requirements Analysis): 2 days, Depends on: None - Task B (Design): 3 days, Depends on: A - Task C (Database Setup): 2 days, Depends on: A - Task D (Development): 5 days, Depends on: B, C - Task E (Testing): 3 days, Depends on: D What is the minimum number of days required to complete the entire project?
Step-by-step solution:

Critical Path Method (CPM):
1. Identify dependencies and calculate earliest start times:
- Task A: Starts on Day 0, Duration 2 days
Finishes on Day 2
- Task B: Starts on Day 2, Duration 3 days
Finishes on Day 5
- Task C: Starts on Day 2, Duration 2 days
Finishes on Day 4
- Task D: Starts on Day 5, Duration 5 days
Finishes on Day 10
- Task E: Starts on Day 10, Duration 3 days
Finishes on Day 13

2. Task timeline:
Task A: Days 0-2
Task B: Days 2-5 (after A)
Task C: Days 2-4 (after A)
Task D: Days 5-10 (after B and C)
Task E: Days 10-13 (after D)

3. Critical path: A -> B -> D -> E (or A -> C -> D -> E)
4. Total project duration: 13 days

Key Strategy: Calculate earliest start time for each task based on predecessor completion times; the longest path determines total duration.

Question 8

A project consists of the following tasks: - Task A (Requirements Analysis): 2 days, Depends on: None - Task B (Design): 3 days, Depends on: A - Task C (Database Setup): 2 days, Depends on: A - Task D (Development): 5 days, Depends on: B, C - Task E (Testing): 3 days, Depends on: D What is the minimum number of days required to complete the entire project?
Step-by-step solution:

Critical Path Method (CPM):
1. Identify dependencies and calculate earliest start times:
- Task A: Starts on Day 0, Duration 2 days
Finishes on Day 2
- Task B: Starts on Day 2, Duration 3 days
Finishes on Day 5
- Task C: Starts on Day 2, Duration 2 days
Finishes on Day 4
- Task D: Starts on Day 5, Duration 5 days
Finishes on Day 10
- Task E: Starts on Day 10, Duration 3 days
Finishes on Day 13

2. Task timeline:
Task A: Days 0-2
Task B: Days 2-5 (after A)
Task C: Days 2-4 (after A)
Task D: Days 5-10 (after B and C)
Task E: Days 10-13 (after D)

3. Critical path: A -> B -> D -> E (or A -> C -> D -> E)
4. Total project duration: 13 days

Key Strategy: Calculate earliest start time for each task based on predecessor completion times; the longest path determines total duration.

Question 9

A project consists of the following tasks: - Task A (Requirements Analysis): 2 days, Depends on: None - Task B (Design): 3 days, Depends on: A - Task C (Database Setup): 2 days, Depends on: A - Task D (Development): 5 days, Depends on: B, C - Task E (Testing): 3 days, Depends on: D What is the minimum number of days required to complete the entire project?
Step-by-step solution:

Critical Path Method (CPM):
1. Identify dependencies and calculate earliest start times:
- Task A: Starts on Day 0, Duration 2 days
Finishes on Day 2
- Task B: Starts on Day 2, Duration 3 days
Finishes on Day 5
- Task C: Starts on Day 2, Duration 2 days
Finishes on Day 4
- Task D: Starts on Day 5, Duration 5 days
Finishes on Day 10
- Task E: Starts on Day 10, Duration 3 days
Finishes on Day 13

2. Task timeline:
Task A: Days 0-2
Task B: Days 2-5 (after A)
Task C: Days 2-4 (after A)
Task D: Days 5-10 (after B and C)
Task E: Days 10-13 (after D)

3. Critical path: A -> B -> D -> E (or A -> C -> D -> E)
4. Total project duration: 13 days

Key Strategy: Calculate earliest start time for each task based on predecessor completion times; the longest path determines total duration.

Question 10

A project consists of the following tasks: - Task A (Requirements Analysis): 2 days, Depends on: None - Task B (Design): 3 days, Depends on: A - Task C (Database Setup): 2 days, Depends on: A - Task D (Development): 5 days, Depends on: B, C - Task E (Testing): 3 days, Depends on: D What is the minimum number of days required to complete the entire project?
Step-by-step solution:

Critical Path Method (CPM):
1. Identify dependencies and calculate earliest start times:
- Task A: Starts on Day 0, Duration 2 days
Finishes on Day 2
- Task B: Starts on Day 2, Duration 3 days
Finishes on Day 5
- Task C: Starts on Day 2, Duration 2 days
Finishes on Day 4
- Task D: Starts on Day 5, Duration 5 days
Finishes on Day 10
- Task E: Starts on Day 10, Duration 3 days
Finishes on Day 13

2. Task timeline:
Task A: Days 0-2
Task B: Days 2-5 (after A)
Task C: Days 2-4 (after A)
Task D: Days 5-10 (after B and C)
Task E: Days 10-13 (after D)

3. Critical path: A -> B -> D -> E (or A -> C -> D -> E)
4. Total project duration: 13 days

Key Strategy: Calculate earliest start time for each task based on predecessor completion times; the longest path determines total duration.

Question 11

A project consists of the following tasks: - Task A (Requirements Analysis): 2 days, Depends on: None - Task B (Design): 3 days, Depends on: A - Task C (Database Setup): 2 days, Depends on: A - Task D (Development): 5 days, Depends on: B, C - Task E (Testing): 3 days, Depends on: D What is the minimum number of days required to complete the entire project?
Step-by-step solution:

Critical Path Method (CPM):
1. Identify dependencies and calculate earliest start times:
- Task A: Starts on Day 0, Duration 2 days
Finishes on Day 2
- Task B: Starts on Day 2, Duration 3 days
Finishes on Day 5
- Task C: Starts on Day 2, Duration 2 days
Finishes on Day 4
- Task D: Starts on Day 5, Duration 5 days
Finishes on Day 10
- Task E: Starts on Day 10, Duration 3 days
Finishes on Day 13

2. Task timeline:
Task A: Days 0-2
Task B: Days 2-5 (after A)
Task C: Days 2-4 (after A)
Task D: Days 5-10 (after B and C)
Task E: Days 10-13 (after D)

3. Critical path: A -> B -> D -> E (or A -> C -> D -> E)
4. Total project duration: 13 days

Key Strategy: Calculate earliest start time for each task based on predecessor completion times; the longest path determines total duration.

Question 12

A project consists of the following tasks: - Task A (Requirements Analysis): 2 days, Depends on: None - Task B (Design): 3 days, Depends on: A - Task C (Database Setup): 2 days, Depends on: A - Task D (Development): 5 days, Depends on: B, C - Task E (Testing): 3 days, Depends on: D What is the minimum number of days required to complete the entire project?
Step-by-step solution:

Critical Path Method (CPM):
1. Identify dependencies and calculate earliest start times:
- Task A: Starts on Day 0, Duration 2 days
Finishes on Day 2
- Task B: Starts on Day 2, Duration 3 days
Finishes on Day 5
- Task C: Starts on Day 2, Duration 2 days
Finishes on Day 4
- Task D: Starts on Day 5, Duration 5 days
Finishes on Day 10
- Task E: Starts on Day 10, Duration 3 days
Finishes on Day 13

2. Task timeline:
Task A: Days 0-2
Task B: Days 2-5 (after A)
Task C: Days 2-4 (after A)
Task D: Days 5-10 (after B and C)
Task E: Days 10-13 (after D)

3. Critical path: A -> B -> D -> E (or A -> C -> D -> E)
4. Total project duration: 13 days

Key Strategy: Calculate earliest start time for each task based on predecessor completion times; the longest path determines total duration.

Question 13

A project consists of the following tasks: - Task A (Requirements Analysis): 2 days, Depends on: None - Task B (Design): 3 days, Depends on: A - Task C (Database Setup): 2 days, Depends on: A - Task D (Development): 5 days, Depends on: B, C - Task E (Testing): 3 days, Depends on: D What is the minimum number of days required to complete the entire project?
Step-by-step solution:

Critical Path Method (CPM):
1. Identify dependencies and calculate earliest start times:
- Task A: Starts on Day 0, Duration 2 days
Finishes on Day 2
- Task B: Starts on Day 2, Duration 3 days
Finishes on Day 5
- Task C: Starts on Day 2, Duration 2 days
Finishes on Day 4
- Task D: Starts on Day 5, Duration 5 days
Finishes on Day 10
- Task E: Starts on Day 10, Duration 3 days
Finishes on Day 13

2. Task timeline:
Task A: Days 0-2
Task B: Days 2-5 (after A)
Task C: Days 2-4 (after A)
Task D: Days 5-10 (after B and C)
Task E: Days 10-13 (after D)

3. Critical path: A -> B -> D -> E (or A -> C -> D -> E)
4. Total project duration: 13 days

Key Strategy: Calculate earliest start time for each task based on predecessor completion times; the longest path determines total duration.

Question 14

A project consists of the following tasks: - Task A (Requirements Analysis): 2 days, Depends on: None - Task B (Design): 3 days, Depends on: A - Task C (Database Setup): 2 days, Depends on: A - Task D (Development): 5 days, Depends on: B, C - Task E (Testing): 3 days, Depends on: D What is the minimum number of days required to complete the entire project?
Step-by-step solution:

Critical Path Method (CPM):
1. Identify dependencies and calculate earliest start times:
- Task A: Starts on Day 0, Duration 2 days
Finishes on Day 2
- Task B: Starts on Day 2, Duration 3 days
Finishes on Day 5
- Task C: Starts on Day 2, Duration 2 days
Finishes on Day 4
- Task D: Starts on Day 5, Duration 5 days
Finishes on Day 10
- Task E: Starts on Day 10, Duration 3 days
Finishes on Day 13

2. Task timeline:
Task A: Days 0-2
Task B: Days 2-5 (after A)
Task C: Days 2-4 (after A)
Task D: Days 5-10 (after B and C)
Task E: Days 10-13 (after D)

3. Critical path: A -> B -> D -> E (or A -> C -> D -> E)
4. Total project duration: 13 days

Key Strategy: Calculate earliest start time for each task based on predecessor completion times; the longest path determines total duration.

Question 15

A project consists of the following tasks: - Task A (Requirements Analysis): 2 days, Depends on: None - Task B (Design): 3 days, Depends on: A - Task C (Database Setup): 2 days, Depends on: A - Task D (Development): 5 days, Depends on: B, C - Task E (Testing): 3 days, Depends on: D What is the minimum number of days required to complete the entire project?
Step-by-step solution:

Critical Path Method (CPM):
1. Identify dependencies and calculate earliest start times:
- Task A: Starts on Day 0, Duration 2 days
Finishes on Day 2
- Task B: Starts on Day 2, Duration 3 days
Finishes on Day 5
- Task C: Starts on Day 2, Duration 2 days
Finishes on Day 4
- Task D: Starts on Day 5, Duration 5 days
Finishes on Day 10
- Task E: Starts on Day 10, Duration 3 days
Finishes on Day 13

2. Task timeline:
Task A: Days 0-2
Task B: Days 2-5 (after A)
Task C: Days 2-4 (after A)
Task D: Days 5-10 (after B and C)
Task E: Days 10-13 (after D)

3. Critical path: A -> B -> D -> E (or A -> C -> D -> E)
4. Total project duration: 13 days

Key Strategy: Calculate earliest start time for each task based on predecessor completion times; the longest path determines total duration.

Question 16

A project consists of the following tasks: - Task A (Requirements Analysis): 2 days, Depends on: None - Task B (Design): 3 days, Depends on: A - Task C (Database Setup): 2 days, Depends on: A - Task D (Development): 5 days, Depends on: B, C - Task E (Testing): 3 days, Depends on: D What is the minimum number of days required to complete the entire project?
Step-by-step solution:

Critical Path Method (CPM):
1. Identify dependencies and calculate earliest start times:
- Task A: Starts on Day 0, Duration 2 days
Finishes on Day 2
- Task B: Starts on Day 2, Duration 3 days
Finishes on Day 5
- Task C: Starts on Day 2, Duration 2 days
Finishes on Day 4
- Task D: Starts on Day 5, Duration 5 days
Finishes on Day 10
- Task E: Starts on Day 10, Duration 3 days
Finishes on Day 13

2. Task timeline:
Task A: Days 0-2
Task B: Days 2-5 (after A)
Task C: Days 2-4 (after A)
Task D: Days 5-10 (after B and C)
Task E: Days 10-13 (after D)

3. Critical path: A -> B -> D -> E (or A -> C -> D -> E)
4. Total project duration: 13 days

Key Strategy: Calculate earliest start time for each task based on predecessor completion times; the longest path determines total duration.

Question 17

A project consists of the following tasks: - Task A (Requirements Analysis): 2 days, Depends on: None - Task B (Design): 3 days, Depends on: A - Task C (Database Setup): 2 days, Depends on: A - Task D (Development): 5 days, Depends on: B, C - Task E (Testing): 3 days, Depends on: D What is the minimum number of days required to complete the entire project?
Step-by-step solution:

Critical Path Method (CPM):
1. Identify dependencies and calculate earliest start times:
- Task A: Starts on Day 0, Duration 2 days
Finishes on Day 2
- Task B: Starts on Day 2, Duration 3 days
Finishes on Day 5
- Task C: Starts on Day 2, Duration 2 days
Finishes on Day 4
- Task D: Starts on Day 5, Duration 5 days
Finishes on Day 10
- Task E: Starts on Day 10, Duration 3 days
Finishes on Day 13

2. Task timeline:
Task A: Days 0-2
Task B: Days 2-5 (after A)
Task C: Days 2-4 (after A)
Task D: Days 5-10 (after B and C)
Task E: Days 10-13 (after D)

3. Critical path: A -> B -> D -> E (or A -> C -> D -> E)
4. Total project duration: 13 days

Key Strategy: Calculate earliest start time for each task based on predecessor completion times; the longest path determines total duration.

Question 18

A project consists of the following tasks: - Task A (Requirements Analysis): 2 days, Depends on: None - Task B (Design): 3 days, Depends on: A - Task C (Database Setup): 2 days, Depends on: A - Task D (Development): 5 days, Depends on: B, C - Task E (Testing): 3 days, Depends on: D What is the minimum number of days required to complete the entire project?
Step-by-step solution:

Critical Path Method (CPM):
1. Identify dependencies and calculate earliest start times:
- Task A: Starts on Day 0, Duration 2 days
Finishes on Day 2
- Task B: Starts on Day 2, Duration 3 days
Finishes on Day 5
- Task C: Starts on Day 2, Duration 2 days
Finishes on Day 4
- Task D: Starts on Day 5, Duration 5 days
Finishes on Day 10
- Task E: Starts on Day 10, Duration 3 days
Finishes on Day 13

2. Task timeline:
Task A: Days 0-2
Task B: Days 2-5 (after A)
Task C: Days 2-4 (after A)
Task D: Days 5-10 (after B and C)
Task E: Days 10-13 (after D)

3. Critical path: A -> B -> D -> E (or A -> C -> D -> E)
4. Total project duration: 13 days

Key Strategy: Calculate earliest start time for each task based on predecessor completion times; the longest path determines total duration.

Question 19

A project consists of the following tasks: - Task A (Requirements Analysis): 2 days, Depends on: None - Task B (Design): 3 days, Depends on: A - Task C (Database Setup): 2 days, Depends on: A - Task D (Development): 5 days, Depends on: B, C - Task E (Testing): 3 days, Depends on: D What is the minimum number of days required to complete the entire project?
Step-by-step solution:

Critical Path Method (CPM):
1. Identify dependencies and calculate earliest start times:
- Task A: Starts on Day 0, Duration 2 days
Finishes on Day 2
- Task B: Starts on Day 2, Duration 3 days
Finishes on Day 5
- Task C: Starts on Day 2, Duration 2 days
Finishes on Day 4
- Task D: Starts on Day 5, Duration 5 days
Finishes on Day 10
- Task E: Starts on Day 10, Duration 3 days
Finishes on Day 13

2. Task timeline:
Task A: Days 0-2
Task B: Days 2-5 (after A)
Task C: Days 2-4 (after A)
Task D: Days 5-10 (after B and C)
Task E: Days 10-13 (after D)

3. Critical path: A -> B -> D -> E (or A -> C -> D -> E)
4. Total project duration: 13 days

Key Strategy: Calculate earliest start time for each task based on predecessor completion times; the longest path determines total duration.

Question 20

A project consists of the following tasks: - Task A (Requirements Analysis): 2 days, Depends on: None - Task B (Design): 3 days, Depends on: A - Task C (Database Setup): 2 days, Depends on: A - Task D (Development): 5 days, Depends on: B, C - Task E (Testing): 3 days, Depends on: D What is the minimum number of days required to complete the entire project?
Step-by-step solution:

Critical Path Method (CPM):
1. Identify dependencies and calculate earliest start times:
- Task A: Starts on Day 0, Duration 2 days
Finishes on Day 2
- Task B: Starts on Day 2, Duration 3 days
Finishes on Day 5
- Task C: Starts on Day 2, Duration 2 days
Finishes on Day 4
- Task D: Starts on Day 5, Duration 5 days
Finishes on Day 10
- Task E: Starts on Day 10, Duration 3 days
Finishes on Day 13

2. Task timeline:
Task A: Days 0-2
Task B: Days 2-5 (after A)
Task C: Days 2-4 (after A)
Task D: Days 5-10 (after B and C)
Task E: Days 10-13 (after D)

3. Critical path: A -> B -> D -> E (or A -> C -> D -> E)
4. Total project duration: 13 days

Key Strategy: Calculate earliest start time for each task based on predecessor completion times; the longest path determines total duration.
Previous Worksheet Next Worksheet