Project Task Dependency
Project Task Dependency problems involve scheduling tasks that have dependencies (some tasks must finish before others can start). You need to find the minimum project completion time using Critical Path Method (CPM) by calculating earliest start and finish times.
What You'll Learn
Introduction to Project Task Dependency
Project Task Dependency problems involve scheduling tasks that have dependencies (some tasks must finish before others can start). You need to find the minimum project completion time using Critical Path Method (CPM) by calculating earliest start and finish times.
Prerequisites
How to Solve Project Task Dependency Problems
Step 1: List all tasks with durations and dependencies
Step 2: Calculate earliest start time for each task (max of predecessors' finish times)
Step 3: Calculate earliest finish time = earliest start + duration
Step 4: The project duration = max of all earliest finish times
Step 5: Identify critical path (tasks with zero slack)
Step 6: Answer with minimum project duration
Example Problem
Example: Task A (2 days, no dependency), Task B (3 days, depends on A), Task C (2 days, depends on A), Task D (5 days, depends on B and C), Task E (3 days, depends on D). Minimum project duration? Solution: Step 1: A: ES=0, EF=2 Step 2: B: ES=2 (after A), EF=5; C: ES=2, EF=4 Step 3: D: ES=max(5,4)=5, EF=10 Step 4: E: ES=10, EF=13 Step 5: Project duration = 13 days Answer: 13 days
Pro Tips & Tricks
- Draw a network diagram with nodes as tasks and arrows as dependencies
- Tasks with no dependencies have ES=0
- If a task has multiple predecessors, ES = max(EF of all predecessors)
- The critical path is the longest path through the network
- Critical path determines minimum project duration
- Slack = LS - ES (tasks on critical path have slack = 0)
Shortcut Methods to Solve Faster
Common Mistakes to Avoid
Practice Worksheets
Practice makes perfect! Work through these worksheets to master Project Task Dependency. Each worksheet contains 20 questions with detailed explanations. Start from Worksheet 1 and progress through increasing difficulty levels.
Exam Importance
Project Task Dependency is an important topic for various competitive exams. Here's how frequently it appears:
Ready to Master Project Task Dependency?
Start with Worksheet 1 and work your way up to expert level! Each worksheet includes: