Question 1
A machine can process up to 6 jobs simultaneously as a batch. Each batch takes 52 minutes. If 17 jobs need to be processed, what is the minimum total time required?
Step-by-step solution:
1. Jobs per batch: 6
2. Number of batches: ⌈17 ÷ 6⌉ = 3
3. Total time: 3 × 52 = 156 minutes
Answer: 156 minutes