Question 1
A machine can process up to 6 jobs simultaneously as a batch. Each batch takes 49 minutes. If 20 jobs need to be processed, what is the minimum total time required?
Step-by-step solution:
1. Jobs per batch: 6
2. Number of batches: โ20 รท 6โ = 4
3. Total time: 4 ร 49 = 196 minutes
Answer: 196 minutes