Time Slot Minimum Gap - Absolute-Beginner Level: core concept mastery Time Slot Minimum Gap ABSOLUTE BEGINNER

This skill primer 🌟 worksheet focuses on Time Slot Minimum Gap - a key topic in Scheduling. You'll solve 20 absolute-beginner-level problems (Worksheet 1 of 10). The primary focus is on core concept mastery. Master time slot minimum gap problems, time slot minimum gap reasoning questions, and time slot minimum gap practice through systematic practice.

📝 Worksheet 1 of 10 • 20 questions • ⏱️ Estimated time: 20 minutes • 🎯 Absolute Beginner level

What you'll learn in this worksheet:
Your progress through Time Slot Minimum Gap
Worksheet 1 of 10 (0% complete)

Question 1

A project involves two events, Event A (Meeting) and Event B (Training). The constraints are: - **Event A:** Duration 90 minutes. Must start between 9:00 AM and 11:00 AM. - **Event B:** Duration 60 minutes. Must finish by 3:00 PM. - **Gap:** A minimum of 2 hours is required between the end of Event A and the start of Event B. Assuming all constraints must be met, what is the earliest possible start time for Event B?
Step-by-step solution (Time Arithmetic):

1. Goal: To find the earliest start time for Event B, we must use the earliest possible schedule for Event A.
2. Calculate Earliest Finish Time for Event A:
- Earliest Start for A: 9:00 AM
- Duration of A: 90 minutes (1 hour 30 minutes)
- Earliest Finish for A: 9:00 AM + 1 hour 30 minutes = 10:30 AM.
3. Apply Minimum Gap:
- Earliest Start for B = (Earliest Finish A) + (Minimum Gap)
- Minimum Gap: 2 hours (120 minutes)
- Earliest Start for B: 10:30 AM + 2 hours = 12:30 PM.
4. Check Deadline for Event B:
- If B starts at 12:30 PM, its finish time is 12:30 PM + 60 minutes = 1:30 PM.
- The latest finish time for B is 3:00 PM. Since 1:30 PM is before 3:00 PM, the schedule is valid.
Answer: The earliest possible start time for Event B is 12:30 PM.
Key Strategy: To find the minimum time for the second event, use the minimum time for the first event, plus the mandatory gap.

Question 2

A project involves two events, Event A (Meeting) and Event B (Training). The constraints are: - **Event A:** Duration 90 minutes. Must start between 9:00 AM and 11:00 AM. - **Event B:** Duration 60 minutes. Must finish by 3:00 PM. - **Gap:** A minimum of 2 hours is required between the end of Event A and the start of Event B. Assuming all constraints must be met, what is the earliest possible start time for Event B?
Step-by-step solution (Time Arithmetic):

1. Goal: To find the earliest start time for Event B, we must use the earliest possible schedule for Event A.
2. Calculate Earliest Finish Time for Event A:
- Earliest Start for A: 9:00 AM
- Duration of A: 90 minutes (1 hour 30 minutes)
- Earliest Finish for A: 9:00 AM + 1 hour 30 minutes = 10:30 AM.
3. Apply Minimum Gap:
- Earliest Start for B = (Earliest Finish A) + (Minimum Gap)
- Minimum Gap: 2 hours (120 minutes)
- Earliest Start for B: 10:30 AM + 2 hours = 12:30 PM.
4. Check Deadline for Event B:
- If B starts at 12:30 PM, its finish time is 12:30 PM + 60 minutes = 1:30 PM.
- The latest finish time for B is 3:00 PM. Since 1:30 PM is before 3:00 PM, the schedule is valid.
Answer: The earliest possible start time for Event B is 12:30 PM.
Key Strategy: To find the minimum time for the second event, use the minimum time for the first event, plus the mandatory gap.

Question 3

A project involves two events, Event A (Meeting) and Event B (Training). The constraints are: - **Event A:** Duration 90 minutes. Must start between 9:00 AM and 11:00 AM. - **Event B:** Duration 60 minutes. Must finish by 3:00 PM. - **Gap:** A minimum of 2 hours is required between the end of Event A and the start of Event B. Assuming all constraints must be met, what is the earliest possible start time for Event B?
Step-by-step solution (Time Arithmetic):

1. Goal: To find the earliest start time for Event B, we must use the earliest possible schedule for Event A.
2. Calculate Earliest Finish Time for Event A:
- Earliest Start for A: 9:00 AM
- Duration of A: 90 minutes (1 hour 30 minutes)
- Earliest Finish for A: 9:00 AM + 1 hour 30 minutes = 10:30 AM.
3. Apply Minimum Gap:
- Earliest Start for B = (Earliest Finish A) + (Minimum Gap)
- Minimum Gap: 2 hours (120 minutes)
- Earliest Start for B: 10:30 AM + 2 hours = 12:30 PM.
4. Check Deadline for Event B:
- If B starts at 12:30 PM, its finish time is 12:30 PM + 60 minutes = 1:30 PM.
- The latest finish time for B is 3:00 PM. Since 1:30 PM is before 3:00 PM, the schedule is valid.
Answer: The earliest possible start time for Event B is 12:30 PM.
Key Strategy: To find the minimum time for the second event, use the minimum time for the first event, plus the mandatory gap.

Question 4

A project involves two events, Event A (Meeting) and Event B (Training). The constraints are: - **Event A:** Duration 90 minutes. Must start between 9:00 AM and 11:00 AM. - **Event B:** Duration 60 minutes. Must finish by 3:00 PM. - **Gap:** A minimum of 2 hours is required between the end of Event A and the start of Event B. Assuming all constraints must be met, what is the earliest possible start time for Event B?
Step-by-step solution (Time Arithmetic):

1. Goal: To find the earliest start time for Event B, we must use the earliest possible schedule for Event A.
2. Calculate Earliest Finish Time for Event A:
- Earliest Start for A: 9:00 AM
- Duration of A: 90 minutes (1 hour 30 minutes)
- Earliest Finish for A: 9:00 AM + 1 hour 30 minutes = 10:30 AM.
3. Apply Minimum Gap:
- Earliest Start for B = (Earliest Finish A) + (Minimum Gap)
- Minimum Gap: 2 hours (120 minutes)
- Earliest Start for B: 10:30 AM + 2 hours = 12:30 PM.
4. Check Deadline for Event B:
- If B starts at 12:30 PM, its finish time is 12:30 PM + 60 minutes = 1:30 PM.
- The latest finish time for B is 3:00 PM. Since 1:30 PM is before 3:00 PM, the schedule is valid.
Answer: The earliest possible start time for Event B is 12:30 PM.
Key Strategy: To find the minimum time for the second event, use the minimum time for the first event, plus the mandatory gap.

Question 5

A project involves two events, Event A (Meeting) and Event B (Training). The constraints are: - **Event A:** Duration 90 minutes. Must start between 9:00 AM and 11:00 AM. - **Event B:** Duration 60 minutes. Must finish by 3:00 PM. - **Gap:** A minimum of 2 hours is required between the end of Event A and the start of Event B. Assuming all constraints must be met, what is the earliest possible start time for Event B?
Step-by-step solution (Time Arithmetic):

1. Goal: To find the earliest start time for Event B, we must use the earliest possible schedule for Event A.
2. Calculate Earliest Finish Time for Event A:
- Earliest Start for A: 9:00 AM
- Duration of A: 90 minutes (1 hour 30 minutes)
- Earliest Finish for A: 9:00 AM + 1 hour 30 minutes = 10:30 AM.
3. Apply Minimum Gap:
- Earliest Start for B = (Earliest Finish A) + (Minimum Gap)
- Minimum Gap: 2 hours (120 minutes)
- Earliest Start for B: 10:30 AM + 2 hours = 12:30 PM.
4. Check Deadline for Event B:
- If B starts at 12:30 PM, its finish time is 12:30 PM + 60 minutes = 1:30 PM.
- The latest finish time for B is 3:00 PM. Since 1:30 PM is before 3:00 PM, the schedule is valid.
Answer: The earliest possible start time for Event B is 12:30 PM.
Key Strategy: To find the minimum time for the second event, use the minimum time for the first event, plus the mandatory gap.

Question 6

A project involves two events, Event A (Meeting) and Event B (Training). The constraints are: - **Event A:** Duration 90 minutes. Must start between 9:00 AM and 11:00 AM. - **Event B:** Duration 60 minutes. Must finish by 3:00 PM. - **Gap:** A minimum of 2 hours is required between the end of Event A and the start of Event B. Assuming all constraints must be met, what is the earliest possible start time for Event B?
Step-by-step solution (Time Arithmetic):

1. Goal: To find the earliest start time for Event B, we must use the earliest possible schedule for Event A.
2. Calculate Earliest Finish Time for Event A:
- Earliest Start for A: 9:00 AM
- Duration of A: 90 minutes (1 hour 30 minutes)
- Earliest Finish for A: 9:00 AM + 1 hour 30 minutes = 10:30 AM.
3. Apply Minimum Gap:
- Earliest Start for B = (Earliest Finish A) + (Minimum Gap)
- Minimum Gap: 2 hours (120 minutes)
- Earliest Start for B: 10:30 AM + 2 hours = 12:30 PM.
4. Check Deadline for Event B:
- If B starts at 12:30 PM, its finish time is 12:30 PM + 60 minutes = 1:30 PM.
- The latest finish time for B is 3:00 PM. Since 1:30 PM is before 3:00 PM, the schedule is valid.
Answer: The earliest possible start time for Event B is 12:30 PM.
Key Strategy: To find the minimum time for the second event, use the minimum time for the first event, plus the mandatory gap.

Question 7

A project involves two events, Event A (Meeting) and Event B (Training). The constraints are: - **Event A:** Duration 90 minutes. Must start between 9:00 AM and 11:00 AM. - **Event B:** Duration 60 minutes. Must finish by 3:00 PM. - **Gap:** A minimum of 2 hours is required between the end of Event A and the start of Event B. Assuming all constraints must be met, what is the earliest possible start time for Event B?
Step-by-step solution (Time Arithmetic):

1. Goal: To find the earliest start time for Event B, we must use the earliest possible schedule for Event A.
2. Calculate Earliest Finish Time for Event A:
- Earliest Start for A: 9:00 AM
- Duration of A: 90 minutes (1 hour 30 minutes)
- Earliest Finish for A: 9:00 AM + 1 hour 30 minutes = 10:30 AM.
3. Apply Minimum Gap:
- Earliest Start for B = (Earliest Finish A) + (Minimum Gap)
- Minimum Gap: 2 hours (120 minutes)
- Earliest Start for B: 10:30 AM + 2 hours = 12:30 PM.
4. Check Deadline for Event B:
- If B starts at 12:30 PM, its finish time is 12:30 PM + 60 minutes = 1:30 PM.
- The latest finish time for B is 3:00 PM. Since 1:30 PM is before 3:00 PM, the schedule is valid.
Answer: The earliest possible start time for Event B is 12:30 PM.
Key Strategy: To find the minimum time for the second event, use the minimum time for the first event, plus the mandatory gap.

Question 8

A project involves two events, Event A (Meeting) and Event B (Training). The constraints are: - **Event A:** Duration 90 minutes. Must start between 9:00 AM and 11:00 AM. - **Event B:** Duration 60 minutes. Must finish by 3:00 PM. - **Gap:** A minimum of 2 hours is required between the end of Event A and the start of Event B. Assuming all constraints must be met, what is the earliest possible start time for Event B?
Step-by-step solution (Time Arithmetic):

1. Goal: To find the earliest start time for Event B, we must use the earliest possible schedule for Event A.
2. Calculate Earliest Finish Time for Event A:
- Earliest Start for A: 9:00 AM
- Duration of A: 90 minutes (1 hour 30 minutes)
- Earliest Finish for A: 9:00 AM + 1 hour 30 minutes = 10:30 AM.
3. Apply Minimum Gap:
- Earliest Start for B = (Earliest Finish A) + (Minimum Gap)
- Minimum Gap: 2 hours (120 minutes)
- Earliest Start for B: 10:30 AM + 2 hours = 12:30 PM.
4. Check Deadline for Event B:
- If B starts at 12:30 PM, its finish time is 12:30 PM + 60 minutes = 1:30 PM.
- The latest finish time for B is 3:00 PM. Since 1:30 PM is before 3:00 PM, the schedule is valid.
Answer: The earliest possible start time for Event B is 12:30 PM.
Key Strategy: To find the minimum time for the second event, use the minimum time for the first event, plus the mandatory gap.

Question 9

A project involves two events, Event A (Meeting) and Event B (Training). The constraints are: - **Event A:** Duration 90 minutes. Must start between 9:00 AM and 11:00 AM. - **Event B:** Duration 60 minutes. Must finish by 3:00 PM. - **Gap:** A minimum of 2 hours is required between the end of Event A and the start of Event B. Assuming all constraints must be met, what is the earliest possible start time for Event B?
Step-by-step solution (Time Arithmetic):

1. Goal: To find the earliest start time for Event B, we must use the earliest possible schedule for Event A.
2. Calculate Earliest Finish Time for Event A:
- Earliest Start for A: 9:00 AM
- Duration of A: 90 minutes (1 hour 30 minutes)
- Earliest Finish for A: 9:00 AM + 1 hour 30 minutes = 10:30 AM.
3. Apply Minimum Gap:
- Earliest Start for B = (Earliest Finish A) + (Minimum Gap)
- Minimum Gap: 2 hours (120 minutes)
- Earliest Start for B: 10:30 AM + 2 hours = 12:30 PM.
4. Check Deadline for Event B:
- If B starts at 12:30 PM, its finish time is 12:30 PM + 60 minutes = 1:30 PM.
- The latest finish time for B is 3:00 PM. Since 1:30 PM is before 3:00 PM, the schedule is valid.
Answer: The earliest possible start time for Event B is 12:30 PM.
Key Strategy: To find the minimum time for the second event, use the minimum time for the first event, plus the mandatory gap.

Question 10

A project involves two events, Event A (Meeting) and Event B (Training). The constraints are: - **Event A:** Duration 90 minutes. Must start between 9:00 AM and 11:00 AM. - **Event B:** Duration 60 minutes. Must finish by 3:00 PM. - **Gap:** A minimum of 2 hours is required between the end of Event A and the start of Event B. Assuming all constraints must be met, what is the earliest possible start time for Event B?
Step-by-step solution (Time Arithmetic):

1. Goal: To find the earliest start time for Event B, we must use the earliest possible schedule for Event A.
2. Calculate Earliest Finish Time for Event A:
- Earliest Start for A: 9:00 AM
- Duration of A: 90 minutes (1 hour 30 minutes)
- Earliest Finish for A: 9:00 AM + 1 hour 30 minutes = 10:30 AM.
3. Apply Minimum Gap:
- Earliest Start for B = (Earliest Finish A) + (Minimum Gap)
- Minimum Gap: 2 hours (120 minutes)
- Earliest Start for B: 10:30 AM + 2 hours = 12:30 PM.
4. Check Deadline for Event B:
- If B starts at 12:30 PM, its finish time is 12:30 PM + 60 minutes = 1:30 PM.
- The latest finish time for B is 3:00 PM. Since 1:30 PM is before 3:00 PM, the schedule is valid.
Answer: The earliest possible start time for Event B is 12:30 PM.
Key Strategy: To find the minimum time for the second event, use the minimum time for the first event, plus the mandatory gap.

Question 11

A project involves two events, Event A (Meeting) and Event B (Training). The constraints are: - **Event A:** Duration 90 minutes. Must start between 9:00 AM and 11:00 AM. - **Event B:** Duration 60 minutes. Must finish by 3:00 PM. - **Gap:** A minimum of 2 hours is required between the end of Event A and the start of Event B. Assuming all constraints must be met, what is the earliest possible start time for Event B?
Step-by-step solution (Time Arithmetic):

1. Goal: To find the earliest start time for Event B, we must use the earliest possible schedule for Event A.
2. Calculate Earliest Finish Time for Event A:
- Earliest Start for A: 9:00 AM
- Duration of A: 90 minutes (1 hour 30 minutes)
- Earliest Finish for A: 9:00 AM + 1 hour 30 minutes = 10:30 AM.
3. Apply Minimum Gap:
- Earliest Start for B = (Earliest Finish A) + (Minimum Gap)
- Minimum Gap: 2 hours (120 minutes)
- Earliest Start for B: 10:30 AM + 2 hours = 12:30 PM.
4. Check Deadline for Event B:
- If B starts at 12:30 PM, its finish time is 12:30 PM + 60 minutes = 1:30 PM.
- The latest finish time for B is 3:00 PM. Since 1:30 PM is before 3:00 PM, the schedule is valid.
Answer: The earliest possible start time for Event B is 12:30 PM.
Key Strategy: To find the minimum time for the second event, use the minimum time for the first event, plus the mandatory gap.

Question 12

A project involves two events, Event A (Meeting) and Event B (Training). The constraints are: - **Event A:** Duration 90 minutes. Must start between 9:00 AM and 11:00 AM. - **Event B:** Duration 60 minutes. Must finish by 3:00 PM. - **Gap:** A minimum of 2 hours is required between the end of Event A and the start of Event B. Assuming all constraints must be met, what is the earliest possible start time for Event B?
Step-by-step solution (Time Arithmetic):

1. Goal: To find the earliest start time for Event B, we must use the earliest possible schedule for Event A.
2. Calculate Earliest Finish Time for Event A:
- Earliest Start for A: 9:00 AM
- Duration of A: 90 minutes (1 hour 30 minutes)
- Earliest Finish for A: 9:00 AM + 1 hour 30 minutes = 10:30 AM.
3. Apply Minimum Gap:
- Earliest Start for B = (Earliest Finish A) + (Minimum Gap)
- Minimum Gap: 2 hours (120 minutes)
- Earliest Start for B: 10:30 AM + 2 hours = 12:30 PM.
4. Check Deadline for Event B:
- If B starts at 12:30 PM, its finish time is 12:30 PM + 60 minutes = 1:30 PM.
- The latest finish time for B is 3:00 PM. Since 1:30 PM is before 3:00 PM, the schedule is valid.
Answer: The earliest possible start time for Event B is 12:30 PM.
Key Strategy: To find the minimum time for the second event, use the minimum time for the first event, plus the mandatory gap.

Question 13

A project involves two events, Event A (Meeting) and Event B (Training). The constraints are: - **Event A:** Duration 90 minutes. Must start between 9:00 AM and 11:00 AM. - **Event B:** Duration 60 minutes. Must finish by 3:00 PM. - **Gap:** A minimum of 2 hours is required between the end of Event A and the start of Event B. Assuming all constraints must be met, what is the earliest possible start time for Event B?
Step-by-step solution (Time Arithmetic):

1. Goal: To find the earliest start time for Event B, we must use the earliest possible schedule for Event A.
2. Calculate Earliest Finish Time for Event A:
- Earliest Start for A: 9:00 AM
- Duration of A: 90 minutes (1 hour 30 minutes)
- Earliest Finish for A: 9:00 AM + 1 hour 30 minutes = 10:30 AM.
3. Apply Minimum Gap:
- Earliest Start for B = (Earliest Finish A) + (Minimum Gap)
- Minimum Gap: 2 hours (120 minutes)
- Earliest Start for B: 10:30 AM + 2 hours = 12:30 PM.
4. Check Deadline for Event B:
- If B starts at 12:30 PM, its finish time is 12:30 PM + 60 minutes = 1:30 PM.
- The latest finish time for B is 3:00 PM. Since 1:30 PM is before 3:00 PM, the schedule is valid.
Answer: The earliest possible start time for Event B is 12:30 PM.
Key Strategy: To find the minimum time for the second event, use the minimum time for the first event, plus the mandatory gap.

Question 14

A project involves two events, Event A (Meeting) and Event B (Training). The constraints are: - **Event A:** Duration 90 minutes. Must start between 9:00 AM and 11:00 AM. - **Event B:** Duration 60 minutes. Must finish by 3:00 PM. - **Gap:** A minimum of 2 hours is required between the end of Event A and the start of Event B. Assuming all constraints must be met, what is the earliest possible start time for Event B?
Step-by-step solution (Time Arithmetic):

1. Goal: To find the earliest start time for Event B, we must use the earliest possible schedule for Event A.
2. Calculate Earliest Finish Time for Event A:
- Earliest Start for A: 9:00 AM
- Duration of A: 90 minutes (1 hour 30 minutes)
- Earliest Finish for A: 9:00 AM + 1 hour 30 minutes = 10:30 AM.
3. Apply Minimum Gap:
- Earliest Start for B = (Earliest Finish A) + (Minimum Gap)
- Minimum Gap: 2 hours (120 minutes)
- Earliest Start for B: 10:30 AM + 2 hours = 12:30 PM.
4. Check Deadline for Event B:
- If B starts at 12:30 PM, its finish time is 12:30 PM + 60 minutes = 1:30 PM.
- The latest finish time for B is 3:00 PM. Since 1:30 PM is before 3:00 PM, the schedule is valid.
Answer: The earliest possible start time for Event B is 12:30 PM.
Key Strategy: To find the minimum time for the second event, use the minimum time for the first event, plus the mandatory gap.

Question 15

A project involves two events, Event A (Meeting) and Event B (Training). The constraints are: - **Event A:** Duration 90 minutes. Must start between 9:00 AM and 11:00 AM. - **Event B:** Duration 60 minutes. Must finish by 3:00 PM. - **Gap:** A minimum of 2 hours is required between the end of Event A and the start of Event B. Assuming all constraints must be met, what is the earliest possible start time for Event B?
Step-by-step solution (Time Arithmetic):

1. Goal: To find the earliest start time for Event B, we must use the earliest possible schedule for Event A.
2. Calculate Earliest Finish Time for Event A:
- Earliest Start for A: 9:00 AM
- Duration of A: 90 minutes (1 hour 30 minutes)
- Earliest Finish for A: 9:00 AM + 1 hour 30 minutes = 10:30 AM.
3. Apply Minimum Gap:
- Earliest Start for B = (Earliest Finish A) + (Minimum Gap)
- Minimum Gap: 2 hours (120 minutes)
- Earliest Start for B: 10:30 AM + 2 hours = 12:30 PM.
4. Check Deadline for Event B:
- If B starts at 12:30 PM, its finish time is 12:30 PM + 60 minutes = 1:30 PM.
- The latest finish time for B is 3:00 PM. Since 1:30 PM is before 3:00 PM, the schedule is valid.
Answer: The earliest possible start time for Event B is 12:30 PM.
Key Strategy: To find the minimum time for the second event, use the minimum time for the first event, plus the mandatory gap.

Question 16

A project involves two events, Event A (Meeting) and Event B (Training). The constraints are: - **Event A:** Duration 90 minutes. Must start between 9:00 AM and 11:00 AM. - **Event B:** Duration 60 minutes. Must finish by 3:00 PM. - **Gap:** A minimum of 2 hours is required between the end of Event A and the start of Event B. Assuming all constraints must be met, what is the earliest possible start time for Event B?
Step-by-step solution (Time Arithmetic):

1. Goal: To find the earliest start time for Event B, we must use the earliest possible schedule for Event A.
2. Calculate Earliest Finish Time for Event A:
- Earliest Start for A: 9:00 AM
- Duration of A: 90 minutes (1 hour 30 minutes)
- Earliest Finish for A: 9:00 AM + 1 hour 30 minutes = 10:30 AM.
3. Apply Minimum Gap:
- Earliest Start for B = (Earliest Finish A) + (Minimum Gap)
- Minimum Gap: 2 hours (120 minutes)
- Earliest Start for B: 10:30 AM + 2 hours = 12:30 PM.
4. Check Deadline for Event B:
- If B starts at 12:30 PM, its finish time is 12:30 PM + 60 minutes = 1:30 PM.
- The latest finish time for B is 3:00 PM. Since 1:30 PM is before 3:00 PM, the schedule is valid.
Answer: The earliest possible start time for Event B is 12:30 PM.
Key Strategy: To find the minimum time for the second event, use the minimum time for the first event, plus the mandatory gap.

Question 17

A project involves two events, Event A (Meeting) and Event B (Training). The constraints are: - **Event A:** Duration 90 minutes. Must start between 9:00 AM and 11:00 AM. - **Event B:** Duration 60 minutes. Must finish by 3:00 PM. - **Gap:** A minimum of 2 hours is required between the end of Event A and the start of Event B. Assuming all constraints must be met, what is the earliest possible start time for Event B?
Step-by-step solution (Time Arithmetic):

1. Goal: To find the earliest start time for Event B, we must use the earliest possible schedule for Event A.
2. Calculate Earliest Finish Time for Event A:
- Earliest Start for A: 9:00 AM
- Duration of A: 90 minutes (1 hour 30 minutes)
- Earliest Finish for A: 9:00 AM + 1 hour 30 minutes = 10:30 AM.
3. Apply Minimum Gap:
- Earliest Start for B = (Earliest Finish A) + (Minimum Gap)
- Minimum Gap: 2 hours (120 minutes)
- Earliest Start for B: 10:30 AM + 2 hours = 12:30 PM.
4. Check Deadline for Event B:
- If B starts at 12:30 PM, its finish time is 12:30 PM + 60 minutes = 1:30 PM.
- The latest finish time for B is 3:00 PM. Since 1:30 PM is before 3:00 PM, the schedule is valid.
Answer: The earliest possible start time for Event B is 12:30 PM.
Key Strategy: To find the minimum time for the second event, use the minimum time for the first event, plus the mandatory gap.

Question 18

A project involves two events, Event A (Meeting) and Event B (Training). The constraints are: - **Event A:** Duration 90 minutes. Must start between 9:00 AM and 11:00 AM. - **Event B:** Duration 60 minutes. Must finish by 3:00 PM. - **Gap:** A minimum of 2 hours is required between the end of Event A and the start of Event B. Assuming all constraints must be met, what is the earliest possible start time for Event B?
Step-by-step solution (Time Arithmetic):

1. Goal: To find the earliest start time for Event B, we must use the earliest possible schedule for Event A.
2. Calculate Earliest Finish Time for Event A:
- Earliest Start for A: 9:00 AM
- Duration of A: 90 minutes (1 hour 30 minutes)
- Earliest Finish for A: 9:00 AM + 1 hour 30 minutes = 10:30 AM.
3. Apply Minimum Gap:
- Earliest Start for B = (Earliest Finish A) + (Minimum Gap)
- Minimum Gap: 2 hours (120 minutes)
- Earliest Start for B: 10:30 AM + 2 hours = 12:30 PM.
4. Check Deadline for Event B:
- If B starts at 12:30 PM, its finish time is 12:30 PM + 60 minutes = 1:30 PM.
- The latest finish time for B is 3:00 PM. Since 1:30 PM is before 3:00 PM, the schedule is valid.
Answer: The earliest possible start time for Event B is 12:30 PM.
Key Strategy: To find the minimum time for the second event, use the minimum time for the first event, plus the mandatory gap.

Question 19

A project involves two events, Event A (Meeting) and Event B (Training). The constraints are: - **Event A:** Duration 90 minutes. Must start between 9:00 AM and 11:00 AM. - **Event B:** Duration 60 minutes. Must finish by 3:00 PM. - **Gap:** A minimum of 2 hours is required between the end of Event A and the start of Event B. Assuming all constraints must be met, what is the earliest possible start time for Event B?
Step-by-step solution (Time Arithmetic):

1. Goal: To find the earliest start time for Event B, we must use the earliest possible schedule for Event A.
2. Calculate Earliest Finish Time for Event A:
- Earliest Start for A: 9:00 AM
- Duration of A: 90 minutes (1 hour 30 minutes)
- Earliest Finish for A: 9:00 AM + 1 hour 30 minutes = 10:30 AM.
3. Apply Minimum Gap:
- Earliest Start for B = (Earliest Finish A) + (Minimum Gap)
- Minimum Gap: 2 hours (120 minutes)
- Earliest Start for B: 10:30 AM + 2 hours = 12:30 PM.
4. Check Deadline for Event B:
- If B starts at 12:30 PM, its finish time is 12:30 PM + 60 minutes = 1:30 PM.
- The latest finish time for B is 3:00 PM. Since 1:30 PM is before 3:00 PM, the schedule is valid.
Answer: The earliest possible start time for Event B is 12:30 PM.
Key Strategy: To find the minimum time for the second event, use the minimum time for the first event, plus the mandatory gap.

Question 20

A project involves two events, Event A (Meeting) and Event B (Training). The constraints are: - **Event A:** Duration 90 minutes. Must start between 9:00 AM and 11:00 AM. - **Event B:** Duration 60 minutes. Must finish by 3:00 PM. - **Gap:** A minimum of 2 hours is required between the end of Event A and the start of Event B. Assuming all constraints must be met, what is the earliest possible start time for Event B?
Step-by-step solution (Time Arithmetic):

1. Goal: To find the earliest start time for Event B, we must use the earliest possible schedule for Event A.
2. Calculate Earliest Finish Time for Event A:
- Earliest Start for A: 9:00 AM
- Duration of A: 90 minutes (1 hour 30 minutes)
- Earliest Finish for A: 9:00 AM + 1 hour 30 minutes = 10:30 AM.
3. Apply Minimum Gap:
- Earliest Start for B = (Earliest Finish A) + (Minimum Gap)
- Minimum Gap: 2 hours (120 minutes)
- Earliest Start for B: 10:30 AM + 2 hours = 12:30 PM.
4. Check Deadline for Event B:
- If B starts at 12:30 PM, its finish time is 12:30 PM + 60 minutes = 1:30 PM.
- The latest finish time for B is 3:00 PM. Since 1:30 PM is before 3:00 PM, the schedule is valid.
Answer: The earliest possible start time for Event B is 12:30 PM.
Key Strategy: To find the minimum time for the second event, use the minimum time for the first event, plus the mandatory gap.