Scheduling - Intermediate Level: time allocation INTERMEDIATE

Quick mental agility โ˜… session: 20 intermediate-level scheduling questions. Worksheet 17 of 30 - Focus: time allocation. Practice day scheduling, timetable puzzles, appointment logic with instant feedback. Great for mid-level students needing moderate complexity with mixed patterns practice.

๐Ÿ“ Worksheet 17 of 30 โ€ข 20 questions โ€ข โฑ๏ธ Estimated time: 20 minutes โ€ข ๐ŸŽฏ Intermediate level

What you'll learn in this worksheet:
Your progress through Scheduling
Worksheet 17 of 30 (56% complete)

Question 1

A hospital needs one doctor on-call each day for 30 days. There are 5 doctors: Dr. Brown, Dr. Jones, Dr. Lee, Dr. Patel, Dr. Smith. If the schedule is as fair as possible, how many days will each doctor be on-call?
Step-by-step solution:

1. Total on-call days: 30
2. Base days per doctor: 30 รท 5 = 6 days
3. Remainder: 0 doctor(s) get one extra day

Answer: 6 days each

Question 2

A project involves two events, Event A (Meeting) and Event B (Training). The constraints are: - **Event A:** Duration 90 minutes. Must start between 9:00 AM and 11:00 AM. - **Event B:** Duration 60 minutes. Must finish by 3:00 PM. - **Gap:** A minimum of 2 hours is required between the end of Event A and the start of Event B. Assuming all constraints must be met, what is the earliest possible start time for Event B?
Step-by-step solution (Time Arithmetic):

1. Goal: To find the earliest start time for Event B, we must use the earliest possible schedule for Event A.
2. Calculate Earliest Finish Time for Event A:
- Earliest Start for A: 9:00 AM
- Duration of A: 90 minutes (1 hour 30 minutes)
- Earliest Finish for A: 9:00 AM + 1 hour 30 minutes = 10:30 AM.
3. Apply Minimum Gap:
- Earliest Start for B = (Earliest Finish A) + (Minimum Gap)
- Minimum Gap: 2 hours (120 minutes)
- Earliest Start for B: 10:30 AM + 2 hours = 12:30 PM.
4. Check Deadline for Event B:
- If B starts at 12:30 PM, its finish time is 12:30 PM + 60 minutes = 1:30 PM.
- The latest finish time for B is 3:00 PM. Since 1:30 PM is before 3:00 PM, the schedule is valid.
Answer: The earliest possible start time for Event B is 12:30 PM.
Key Strategy: To find the minimum time for the second event, use the minimum time for the first event, plus the mandatory gap.

Question 3

A factory has 3 production lines: Line 1, Line 2, Line 3. Three products require the following operations: **Product X:** - Cut: 30 min on Line 2 - Assemble: 45 min on Line 1 - Package: 15 min on Line 2 **Product Y:** - Cut: 20 min on Line 1 - Assemble: 60 min on Line 3 - Package: 20 min on Line 1 **Product Z:** - Cut: 40 min on Line 2 - Assemble: 30 min on Line 3 - Package: 25 min on Line 3 All products must be completed (all 3 operations each). Multiple operations can run in parallel on different lines. Which production line is the bottleneck, and what is its total load (in minutes)?
Step-by-step solution (Bottleneck Analysis):

1. Calculate total load per production line:
- Line 1: 85 minutes
- Line 2: 85 minutes
- Line 3: 115 minutes

2. Identify bottleneck: The line with maximum load = Line 3
3. Bottleneck load: 115 minutes

Answer: Line 3 (115 minutes)

Key Strategy: The bottleneck determines maximum throughput; optimize the bottleneck first for overall efficiency.

Question 4

Four team members (Eva, Frank, Charlie, Bob) must be assigned to four unique tasks (Testing, Deployment, Design, Documentation). The assignments must follow these rules: 1. Eva must handle Testing. 2. Frank cannot handle Documentation. 3. Charlie and Bob must be adjacent in (Testing โ†’ Deployment โ†’ Design โ†’ Documentation). Based on the constraints, which statement MUST be true?
No valid schedule found given the constraints. The only guaranteed assignment is: Eva must handle Testing.
If the constraints cannot all be satisfied, fallback is to force rule 1's assignment.

Question 5

In a double round-robin tournament with 6 teams, each team plays every other team twice (once home, once away). How many home matches does each team play?
Step-by-step solution:

1. Total matches per team in double round-robin: 2 ร— (6 - 1) = 10 matches
2. Half are home matches: 10 รท 2 = 5 home matches

Answer: 5 home matches

Question 6

In a round-robin tournament with 6 teams, in Round 4, Team B plays against which team?
Step-by-step solution:

1. Round-robin schedule using circle method
2. Round 4 matches:
- Team C vs Team E
- Team B vs Team F
- Team A vs Team D

3. Team B plays against Team F

Answer: Team F

Question 7

A PhD thesis defense requires all 3 committee members to be present. Their availability (slots 1-8): - Prof. D: Slots 3, 7, 4 - Prof. C: Slots 5, 1, 7, 8 - Prof. E: Slots 8, 2, 6 What is the earliest slot when all can attend?
Step-by-step solution:

1. Find intersection of availability:
Prof. D: [3, 4, 7]
โˆฉ Prof. C: [1, 5, 7, 8]
โˆฉ Prof. E: [2, 6, 8]
= โˆ… (No common slots)

Answer: No common slot available

Question 8

Eight people attend seminars in four different months (January, March, May, July) on two dates (5th and 15th). Two people attend per month. The constraints are: - W attends in March - U attends on the 15th - Exactly two people attend between P and T - S attends in the same month as V In which month does P attend?
Step-by-step solution:

Timeline Grid Method:
1. Create month-date grid:
Jan 5 | Jan 15 | Mar 5 | Mar 15 | May 5 | May 15 | Jul 5 | Jul 15

2. Apply constraints:
- W in March (Mar 5 or Mar 15)
- U on 15th (any month, date 15)
- Two people between P and T
(If P at position 1, T at position 4)
- S and V in same month

3. Systematic placement:
- Place W at Mar 5 (satisfies March constraint)
- Place U at Mar 15 (satisfies 15th constraint)
- For 'two between' constraint: If P at Jan 5, T at Mar 15
- S and V together: May 5 & May 15

4. Verification:
All constraints satisfied with P in March

Key Strategy: Use grid to visualize all slots, apply direct constraints first, then deduce positions using gap constraints.

Question 9

Project scheduling with two objectives: minimize time and minimize cost. - Schedule A: 100 days, $50K - Schedule B: 120 days, $40K - Schedule C: 90 days, $60K - Schedule D: 110 days, $45K - Schedule E: 95 days, $55K Which schedules are on the Pareto frontier (not dominated in both objectives)?
Step-by-step solution:

1. Pareto dominance: Schedule X dominates Y if X is better in at least one objective and not worse in others
2. Pareto frontier schedules: Schedule A, Schedule B, Schedule C, Schedule D, Schedule E

Answer: Schedule A, Schedule B, Schedule C, Schedule D, Schedule E

Question 10

A PhD thesis defense requires all 4 committee members to be present. Their availability (slots 1-8): - Prof. A: Slots 2, 8, 6, 5 - Prof. E: Slots 4, 8, 3, 1 - Prof. C: Slots 3, 8, 1, 7 - Prof. B: Slots 1, 3, 6 What is the earliest slot when all can attend?
Step-by-step solution:

1. Find intersection of availability:
Prof. A: [2, 5, 6, 8]
โˆฉ Prof. E: [1, 3, 4, 8]
โˆฉ Prof. C: [1, 3, 7, 8]
โˆฉ Prof. B: [1, 3, 6]
= โˆ… (No common slots)

Answer: No common slot available

Question 11

A factory has 3 production lines: Line 1, Line 2, Line 3. Three products require the following operations: **Product X:** - Cut: 30 min on Line 3 - Assemble: 45 min on Line 3 - Package: 15 min on Line 3 **Product Y:** - Cut: 20 min on Line 1 - Assemble: 60 min on Line 2 - Package: 20 min on Line 3 **Product Z:** - Cut: 40 min on Line 3 - Assemble: 30 min on Line 3 - Package: 25 min on Line 1 All products must be completed (all 3 operations each). Multiple operations can run in parallel on different lines. Which production line is the bottleneck, and what is its total load (in minutes)?
Step-by-step solution (Bottleneck Analysis):

1. Calculate total load per production line:
- Line 1: 45 minutes
- Line 2: 60 minutes
- Line 3: 180 minutes

2. Identify bottleneck: The line with maximum load = Line 3
3. Bottleneck load: 180 minutes

Answer: Line 3 (180 minutes)

Key Strategy: The bottleneck determines maximum throughput; optimize the bottleneck first for overall efficiency.

Question 12

A project involves two events, Event A (Meeting) and Event B (Training). The constraints are: - **Event A:** Duration 90 minutes. Must start between 9:00 AM and 11:00 AM. - **Event B:** Duration 60 minutes. Must finish by 3:00 PM. - **Gap:** A minimum of 2 hours is required between the end of Event A and the start of Event B. Assuming all constraints must be met, what is the earliest possible start time for Event B?
Step-by-step solution (Time Arithmetic):

1. Goal: To find the earliest start time for Event B, we must use the earliest possible schedule for Event A.
2. Calculate Earliest Finish Time for Event A:
- Earliest Start for A: 9:00 AM
- Duration of A: 90 minutes (1 hour 30 minutes)
- Earliest Finish for A: 9:00 AM + 1 hour 30 minutes = 10:30 AM.
3. Apply Minimum Gap:
- Earliest Start for B = (Earliest Finish A) + (Minimum Gap)
- Minimum Gap: 2 hours (120 minutes)
- Earliest Start for B: 10:30 AM + 2 hours = 12:30 PM.
4. Check Deadline for Event B:
- If B starts at 12:30 PM, its finish time is 12:30 PM + 60 minutes = 1:30 PM.
- The latest finish time for B is 3:00 PM. Since 1:30 PM is before 3:00 PM, the schedule is valid.
Answer: The earliest possible start time for Event B is 12:30 PM.
Key Strategy: To find the minimum time for the second event, use the minimum time for the first event, plus the mandatory gap.

Question 13

A manager has 4 tasks to complete over 8 working hours. The task details are: - Report: Priority High, Duration 3 hours, Deadline 5 hours - Email: Priority Low, Duration 1 hours, Deadline 6 hours - Presentation: Priority High, Duration 2 hours, Deadline 4 hours - Analysis: Priority Medium, Duration 2 hours, Deadline 7 hours If tasks are scheduled based on priority first and deadline second, which task should be completed first?
Step-by-step solution:

Priority-Deadline Scheduling Algorithm:
1. Assign priority weights:
- High = 3, Medium = 2, Low = 1

2. Create priority-deadline table:
Task | Priority | Deadline | Duration
--------------|----------|----------|----------
Report | High | 5 | 3
Email | Low | 6 | 1
Presentation | High | 4 | 2
Analysis | Medium | 7 | 2

3. Sorting criteria:
- Primary: Highest priority first
- Secondary: Earliest deadline (if priority is same)

4. Sorted order:
1. Presentation (Priority: High, Deadline: 4)
2. Report (Priority: High, Deadline: 5)
3. Analysis (Priority: Medium, Deadline: 7)
4. Email (Priority: Low, Deadline: 6)

Answer: Presentation should be completed first

Key Strategy: Sort by priority first (descending), then by deadline (ascending) for tasks with equal priority.

Question 14

A flow shop has 2 machines (M1 โ†’ M2). Jobs and processing times (M1, M2): - Job A: (45, 49) - Job B: (37, 37) - Job C: (23, 45) - Job D: (41, 33) - Job E: (27, 26) - Job F: (20, 36) Using Johnson's Rule, what is the minimum makespan?
Step-by-step solution (Johnson's Rule):

1. Apply Johnson's Rule:
- If M1 time < M2 time, schedule early
- If M2 time < M1 time, schedule late
2. Optimal sequence: Job D โ†’ Job E โ†’ Job F โ†’ Job C โ†’ Job B โ†’ Job A
3. Calculate makespan: 267

Answer: 267

Question 15

A hospital needs one doctor on-call each day for 30 days. There are 4 doctors: Dr. Smith, Dr. Brown, Dr. Lee, Dr. Patel. If the schedule is as fair as possible, how many days will each doctor be on-call?
Step-by-step solution:

1. Total on-call days: 30
2. Base days per doctor: 30 รท 4 = 7 days
3. Remainder: 2 doctor(s) get one extra day

Answer: 7 days, with 2 doctor(s) getting 8 days

Question 16

A student has 9 days to prepare for three exams: Mathematics, Computer Science, Chemistry. The required preparation days are: - Mathematics: 3 days - Computer Science: 1 days - Chemistry: 2 days If the student follows the optimal schedule starting today, on which day will the last exam be?
Step-by-step solution:

Timeline Planning Method:
1. Calculate total preparation time needed:
- Mathematics: 3 days
- Computer Science: 1 days
- Chemistry: 2 days
- Total: 6 days

2. Available days: 9 days
3. Extra buffer days: 3 days
4. Optimal schedule:
- Days 1-3: Prepare for Mathematics
- Day 4: Mathematics exam
- Days 5-5: Prepare for Computer Science
- Day 6: Computer Science exam
- Days 7-8: Prepare for Chemistry
- Day 9: Chemistry exam

Answer: The last exam will be on Day 9

Key Strategy: Schedule exams immediately after preparation period ends, accounting for all required prep days.

Question 17

In a single-elimination knockout tournament with 8 teams, how many total matches are played to determine the champion?
Step-by-step solution:

1. Single elimination principle: Each match eliminates exactly one team
2. Teams to eliminate: 8 - 1 = 7 teams must be eliminated
3. Matches needed: 7 matches

Answer: 7 matches

Question 18

5 tasks (A, B, C, D, E) are to be completed one after the other. The following conditions must be met: - Task C must be performed immediately after Task A. - Task B must be completed before Task E. - Task D is neither the first nor the last task to be completed. - Task B is performed exactly 2 positions after Task E. Which task is scheduled in the fourth position?
Step-by-step solution (Deductive Logic):

1. Apply Consecutive Constraint: 'C immediately after A' -> (A, C)
2. Apply Before Constraint: 'B before E'
3. Apply Exclusion Constraint: 'D not first or last'
4. Apply Gap Constraints: 'B is 2 after E'

Final Sequence: A โ†’ C โ†’ B โ†’ D โ†’ E

Answer: The task in the fourth position is D.

Key Strategy: Use fixed pairs and gap constraints to anchor positions.

Question 19

Project tasks with uncertain durations (optimistic, likely, pessimistic) in days: - Design: (3, 5, 8) - Development: (2, 3, 5) - Testing: (4, 7, 9) - Deployment: (2, 5, 6) Using the PERT formula (O + 4M + P)/6, what is the expected total project duration?
Step-by-step solution (PERT):

1. Calculate expected duration for each task:
- Design: (3 + 4ร—5 + 8)/6 = 5.2
- Development: (2 + 4ร—3 + 5)/6 = 3.2
- Testing: (4 + 4ร—7 + 9)/6 = 6.8
- Deployment: (2 + 4ร—5 + 6)/6 = 4.7

2. Total expected duration: 19.8 days

Answer: 19.8 days

Question 20

Hospital OR scheduling with 3 operating rooms (8 hours each): - Emergency: 44 min, Priority 1 - Urgent: 54 min, Priority 2 - Elective A: 113 min, Priority 3 - Elective B: 102 min, Priority 3 - Routine: 136 min, Priority 4 Can all surgeries be completed in one day?
Step-by-step solution:

1. Total surgery time: 449 min = 7.5 hours
2. Available OR hours: 3 ร— 8 = 24 hours
3. Total โ‰ค Available โ†’ Can complete in one day

Answer: All surgeries can be scheduled within one day
Previous Worksheet Next Worksheet