Question 1
Round Robin scheduling with time quantum = 3:
- P1: Burst time 15
- P2: Burst time 6
- P3: Burst time 7
- P4: Burst time 12
What is the average completion time?
Step-by-step solution:
1. Round Robin simulation:
2. Completion times:
- P2: 18
- P3: 28
- P4: 37
- P1: 40
3. Average: 123 รท 4 = 30.8
Answer: 30.8