Learning Curve Scheduling: Worksheet 6 - Intermediate-Advanced Practice Learning Curve Scheduling INTERMEDIATE ADVANCED

Ready to master Learning Curve Scheduling? This timed practice ⚡ worksheet (6/10) presents 20 intermediate-advanced-level challenges. Focus area: speed building. Learn to solve learning curve scheduling tricks, handle learning curve scheduling shortcut methods, and perfect learning curve scheduling bank exam questions with our step-by-step solutions.

📝 Worksheet 6 of 10 • 20 questions • ⏱️ Estimated time: 20 minutes • 🎯 Intermediate Advanced level

What you'll learn in this worksheet:
Your progress through Learning Curve Scheduling
Worksheet 6 of 10 (55% complete)

Question 1

A factory produces Widgets with a 90% learning curve (each doubling of cumulative production reduces time by 9%). First unit takes 97 minutes. Batch sizes (in order): 20, 10, 30 units. What is the TOTAL production time for all batches (in minutes, rounded to nearest minute)?
Step-by-step solution (Learning Curve):

1. Learning curve formula: T_n = T_1 × n^-0.152
where exponent = log(0.9)/log(2) = -0.152

2. Calculate cumulative time using integration:
Cumulative time for N units = T_1 × N^0.84799690655495 / (learning_exponent + 1)

3. Time per batch:
Batch 1 (20 units): 72.5 minutes
Batch 2 (10 units): 59.5 minutes
Batch 3 (30 units): 54.6 minutes

4. Total time: 186.7 ≈ 187 minutes

Key Strategy: Learning curve reduces time with repetition; use cumulative average method for batch calculations.

Question 2

A factory produces Widgets with a 85% learning curve (each doubling of cumulative production reduces time by 15%). First unit takes 83 minutes. Batch sizes (in order): 30, 20, 40 units. What is the TOTAL production time for all batches (in minutes, rounded to nearest minute)?
Step-by-step solution (Learning Curve):

1. Learning curve formula: T_n = T_1 × n^-0.234
where exponent = log(0.85)/log(2) = -0.234

2. Calculate cumulative time using integration:
Cumulative time for N units = T_1 × N^0.765534746362977 / (learning_exponent + 1)

3. Time per batch:
Batch 1 (30 units): 48.8 minutes
Batch 2 (20 units): 35.1 minutes
Batch 3 (40 units): 30.8 minutes

4. Total time: 114.7 ≈ 115 minutes

Key Strategy: Learning curve reduces time with repetition; use cumulative average method for batch calculations.

Question 3

A factory produces Widgets with a 80% learning curve (each doubling of cumulative production reduces time by 19%). First unit takes 108 minutes. Batch sizes (in order): 40, 30, 20 units. What is the TOTAL production time for all batches (in minutes, rounded to nearest minute)?
Step-by-step solution (Learning Curve):

1. Learning curve formula: T_n = T_1 × n^-0.322
where exponent = log(0.8)/log(2) = -0.322

2. Calculate cumulative time using integration:
Cumulative time for N units = T_1 × N^0.6780719051126377 / (learning_exponent + 1)

3. Time per batch:
Batch 1 (40 units): 48.6 minutes
Batch 2 (30 units): 29.9 minutes
Batch 3 (20 units): 26.4 minutes

4. Total time: 104.8 ≈ 105 minutes

Key Strategy: Learning curve reduces time with repetition; use cumulative average method for batch calculations.

Question 4

A factory produces Widgets with a 80% learning curve (each doubling of cumulative production reduces time by 19%). First unit takes 74 minutes. Batch sizes (in order): 20, 10, 30 units. What is the TOTAL production time for all batches (in minutes, rounded to nearest minute)?
Step-by-step solution (Learning Curve):

1. Learning curve formula: T_n = T_1 × n^-0.322
where exponent = log(0.8)/log(2) = -0.322

2. Calculate cumulative time using integration:
Cumulative time for N units = T_1 × N^0.6780719051126377 / (learning_exponent + 1)

3. Time per batch:
Batch 1 (20 units): 41.6 minutes
Batch 2 (10 units): 26.3 minutes
Batch 3 (30 units): 21.9 minutes

4. Total time: 89.8 ≈ 90 minutes

Key Strategy: Learning curve reduces time with repetition; use cumulative average method for batch calculations.

Question 5

A factory produces Widgets with a 80% learning curve (each doubling of cumulative production reduces time by 19%). First unit takes 99 minutes. Batch sizes (in order): 20, 30, 40 units. What is the TOTAL production time for all batches (in minutes, rounded to nearest minute)?
Step-by-step solution (Learning Curve):

1. Learning curve formula: T_n = T_1 × n^-0.322
where exponent = log(0.8)/log(2) = -0.322

2. Calculate cumulative time using integration:
Cumulative time for N units = T_1 × N^0.6780719051126377 / (learning_exponent + 1)

3. Time per batch:
Batch 1 (20 units): 55.7 minutes
Batch 2 (30 units): 32.0 minutes
Batch 3 (40 units): 25.4 minutes

4. Total time: 113.0 ≈ 113 minutes

Key Strategy: Learning curve reduces time with repetition; use cumulative average method for batch calculations.

Question 6

A factory produces Widgets with a 85% learning curve (each doubling of cumulative production reduces time by 15%). First unit takes 66 minutes. Batch sizes (in order): 20, 30, 40 units. What is the TOTAL production time for all batches (in minutes, rounded to nearest minute)?
Step-by-step solution (Learning Curve):

1. Learning curve formula: T_n = T_1 × n^-0.234
where exponent = log(0.85)/log(2) = -0.234

2. Calculate cumulative time using integration:
Cumulative time for N units = T_1 × N^0.765534746362977 / (learning_exponent + 1)

3. Time per batch:
Batch 1 (20 units): 42.7 minutes
Batch 2 (30 units): 28.9 minutes
Batch 3 (40 units): 24.5 minutes

4. Total time: 96.1 ≈ 96 minutes

Key Strategy: Learning curve reduces time with repetition; use cumulative average method for batch calculations.

Question 7

A factory produces Widgets with a 85% learning curve (each doubling of cumulative production reduces time by 15%). First unit takes 106 minutes. Batch sizes (in order): 40, 10, 30 units. What is the TOTAL production time for all batches (in minutes, rounded to nearest minute)?
Step-by-step solution (Learning Curve):

1. Learning curve formula: T_n = T_1 × n^-0.234
where exponent = log(0.85)/log(2) = -0.234

2. Calculate cumulative time using integration:
Cumulative time for N units = T_1 × N^0.765534746362977 / (learning_exponent + 1)

3. Time per batch:
Batch 1 (40 units): 58.3 minutes
Batch 2 (10 units): 43.4 minutes
Batch 3 (30 units): 39.9 minutes

4. Total time: 141.7 ≈ 142 minutes

Key Strategy: Learning curve reduces time with repetition; use cumulative average method for batch calculations.

Question 8

A factory produces Widgets with a 90% learning curve (each doubling of cumulative production reduces time by 9%). First unit takes 73 minutes. Batch sizes (in order): 10, 30, 20 units. What is the TOTAL production time for all batches (in minutes, rounded to nearest minute)?
Step-by-step solution (Learning Curve):

1. Learning curve formula: T_n = T_1 × n^-0.152
where exponent = log(0.9)/log(2) = -0.152

2. Calculate cumulative time using integration:
Cumulative time for N units = T_1 × N^0.84799690655495 / (learning_exponent + 1)

3. Time per batch:
Batch 1 (10 units): 60.7 minutes
Batch 2 (30 units): 45.3 minutes
Batch 3 (20 units): 40.3 minutes

4. Total time: 146.3 ≈ 146 minutes

Key Strategy: Learning curve reduces time with repetition; use cumulative average method for batch calculations.

Question 9

A factory produces Widgets with a 85% learning curve (each doubling of cumulative production reduces time by 15%). First unit takes 93 minutes. Batch sizes (in order): 20, 10, 40 units. What is the TOTAL production time for all batches (in minutes, rounded to nearest minute)?
Step-by-step solution (Learning Curve):

1. Learning curve formula: T_n = T_1 × n^-0.234
where exponent = log(0.85)/log(2) = -0.234

2. Calculate cumulative time using integration:
Cumulative time for N units = T_1 × N^0.765534746362977 / (learning_exponent + 1)

3. Time per batch:
Batch 1 (20 units): 60.2 minutes
Batch 2 (10 units): 43.8 minutes
Batch 3 (40 units): 37.5 minutes

4. Total time: 141.5 ≈ 141 minutes

Key Strategy: Learning curve reduces time with repetition; use cumulative average method for batch calculations.

Question 10

A factory produces Widgets with a 80% learning curve (each doubling of cumulative production reduces time by 19%). First unit takes 92 minutes. Batch sizes (in order): 40, 10, 20 units. What is the TOTAL production time for all batches (in minutes, rounded to nearest minute)?
Step-by-step solution (Learning Curve):

1. Learning curve formula: T_n = T_1 × n^-0.322
where exponent = log(0.8)/log(2) = -0.322

2. Calculate cumulative time using integration:
Cumulative time for N units = T_1 × N^0.6780719051126377 / (learning_exponent + 1)

3. Time per batch:
Batch 1 (40 units): 41.4 minutes
Batch 2 (10 units): 27.0 minutes
Batch 3 (20 units): 24.7 minutes

4. Total time: 93.1 ≈ 93 minutes

Key Strategy: Learning curve reduces time with repetition; use cumulative average method for batch calculations.

Question 11

A factory produces Widgets with a 85% learning curve (each doubling of cumulative production reduces time by 15%). First unit takes 93 minutes. Batch sizes (in order): 40, 20, 30 units. What is the TOTAL production time for all batches (in minutes, rounded to nearest minute)?
Step-by-step solution (Learning Curve):

1. Learning curve formula: T_n = T_1 × n^-0.234
where exponent = log(0.85)/log(2) = -0.234

2. Calculate cumulative time using integration:
Cumulative time for N units = T_1 × N^0.765534746362977 / (learning_exponent + 1)

3. Time per batch:
Batch 1 (40 units): 51.2 minutes
Batch 2 (20 units): 37.2 minutes
Batch 3 (30 units): 33.9 minutes

4. Total time: 122.3 ≈ 122 minutes

Key Strategy: Learning curve reduces time with repetition; use cumulative average method for batch calculations.

Question 12

A factory produces Widgets with a 80% learning curve (each doubling of cumulative production reduces time by 19%). First unit takes 68 minutes. Batch sizes (in order): 20, 10, 40 units. What is the TOTAL production time for all batches (in minutes, rounded to nearest minute)?
Step-by-step solution (Learning Curve):

1. Learning curve formula: T_n = T_1 × n^-0.322
where exponent = log(0.8)/log(2) = -0.322

2. Calculate cumulative time using integration:
Cumulative time for N units = T_1 × N^0.6780719051126377 / (learning_exponent + 1)

3. Time per batch:
Batch 1 (20 units): 38.2 minutes
Batch 2 (10 units): 24.2 minutes
Batch 3 (40 units): 19.5 minutes

4. Total time: 82.0 ≈ 82 minutes

Key Strategy: Learning curve reduces time with repetition; use cumulative average method for batch calculations.

Question 13

A factory produces Widgets with a 90% learning curve (each doubling of cumulative production reduces time by 9%). First unit takes 88 minutes. Batch sizes (in order): 30, 10, 20 units. What is the TOTAL production time for all batches (in minutes, rounded to nearest minute)?
Step-by-step solution (Learning Curve):

1. Learning curve formula: T_n = T_1 × n^-0.152
where exponent = log(0.9)/log(2) = -0.152

2. Calculate cumulative time using integration:
Cumulative time for N units = T_1 × N^0.84799690655495 / (learning_exponent + 1)

3. Time per batch:
Batch 1 (30 units): 61.9 minutes
Batch 2 (10 units): 51.3 minutes
Batch 3 (20 units): 48.6 minutes

4. Total time: 161.8 ≈ 162 minutes

Key Strategy: Learning curve reduces time with repetition; use cumulative average method for batch calculations.

Question 14

A factory produces Widgets with a 85% learning curve (each doubling of cumulative production reduces time by 15%). First unit takes 78 minutes. Batch sizes (in order): 40, 30, 20 units. What is the TOTAL production time for all batches (in minutes, rounded to nearest minute)?
Step-by-step solution (Learning Curve):

1. Learning curve formula: T_n = T_1 × n^-0.234
where exponent = log(0.85)/log(2) = -0.234

2. Calculate cumulative time using integration:
Cumulative time for N units = T_1 × N^0.765534746362977 / (learning_exponent + 1)

3. Time per batch:
Batch 1 (40 units): 42.9 minutes
Batch 2 (30 units): 30.6 minutes
Batch 3 (20 units): 27.9 minutes

4. Total time: 101.4 ≈ 101 minutes

Key Strategy: Learning curve reduces time with repetition; use cumulative average method for batch calculations.

Question 15

A factory produces Widgets with a 85% learning curve (each doubling of cumulative production reduces time by 15%). First unit takes 79 minutes. Batch sizes (in order): 40, 30, 10 units. What is the TOTAL production time for all batches (in minutes, rounded to nearest minute)?
Step-by-step solution (Learning Curve):

1. Learning curve formula: T_n = T_1 × n^-0.234
where exponent = log(0.85)/log(2) = -0.234

2. Calculate cumulative time using integration:
Cumulative time for N units = T_1 × N^0.765534746362977 / (learning_exponent + 1)

3. Time per batch:
Batch 1 (40 units): 43.5 minutes
Batch 2 (30 units): 31.0 minutes
Batch 3 (10 units): 28.7 minutes

4. Total time: 103.2 ≈ 103 minutes

Key Strategy: Learning curve reduces time with repetition; use cumulative average method for batch calculations.

Question 16

A factory produces Widgets with a 80% learning curve (each doubling of cumulative production reduces time by 19%). First unit takes 79 minutes. Batch sizes (in order): 40, 20, 10 units. What is the TOTAL production time for all batches (in minutes, rounded to nearest minute)?
Step-by-step solution (Learning Curve):

1. Learning curve formula: T_n = T_1 × n^-0.322
where exponent = log(0.8)/log(2) = -0.322

2. Calculate cumulative time using integration:
Cumulative time for N units = T_1 × N^0.6780719051126377 / (learning_exponent + 1)

3. Time per batch:
Batch 1 (40 units): 35.5 minutes
Batch 2 (20 units): 22.5 minutes
Batch 3 (10 units): 20.6 minutes

4. Total time: 78.6 ≈ 79 minutes

Key Strategy: Learning curve reduces time with repetition; use cumulative average method for batch calculations.

Question 17

A factory produces Widgets with a 85% learning curve (each doubling of cumulative production reduces time by 15%). First unit takes 78 minutes. Batch sizes (in order): 20, 30, 10 units. What is the TOTAL production time for all batches (in minutes, rounded to nearest minute)?
Step-by-step solution (Learning Curve):

1. Learning curve formula: T_n = T_1 × n^-0.234
where exponent = log(0.85)/log(2) = -0.234

2. Calculate cumulative time using integration:
Cumulative time for N units = T_1 × N^0.765534746362977 / (learning_exponent + 1)

3. Time per batch:
Batch 1 (20 units): 50.5 minutes
Batch 2 (30 units): 34.2 minutes
Batch 3 (10 units): 30.5 minutes

4. Total time: 115.2 ≈ 115 minutes

Key Strategy: Learning curve reduces time with repetition; use cumulative average method for batch calculations.

Question 18

A factory produces Widgets with a 85% learning curve (each doubling of cumulative production reduces time by 15%). First unit takes 112 minutes. Batch sizes (in order): 10, 20, 30 units. What is the TOTAL production time for all batches (in minutes, rounded to nearest minute)?
Step-by-step solution (Learning Curve):

1. Learning curve formula: T_n = T_1 × n^-0.234
where exponent = log(0.85)/log(2) = -0.234

2. Calculate cumulative time using integration:
Cumulative time for N units = T_1 × N^0.765534746362977 / (learning_exponent + 1)

3. Time per batch:
Batch 1 (10 units): 85.3 minutes
Batch 2 (20 units): 56.2 minutes
Batch 3 (30 units): 46.1 minutes

4. Total time: 187.6 ≈ 188 minutes

Key Strategy: Learning curve reduces time with repetition; use cumulative average method for batch calculations.

Question 19

A factory produces Widgets with a 90% learning curve (each doubling of cumulative production reduces time by 9%). First unit takes 71 minutes. Batch sizes (in order): 20, 30, 10 units. What is the TOTAL production time for all batches (in minutes, rounded to nearest minute)?
Step-by-step solution (Learning Curve):

1. Learning curve formula: T_n = T_1 × n^-0.152
where exponent = log(0.9)/log(2) = -0.152

2. Calculate cumulative time using integration:
Cumulative time for N units = T_1 × N^0.84799690655495 / (learning_exponent + 1)

3. Time per batch:
Batch 1 (20 units): 53.1 minutes
Batch 2 (30 units): 41.6 minutes
Batch 3 (10 units): 38.6 minutes

4. Total time: 133.3 ≈ 133 minutes

Key Strategy: Learning curve reduces time with repetition; use cumulative average method for batch calculations.

Question 20

A factory produces Widgets with a 80% learning curve (each doubling of cumulative production reduces time by 19%). First unit takes 67 minutes. Batch sizes (in order): 10, 20, 40 units. What is the TOTAL production time for all batches (in minutes, rounded to nearest minute)?
Step-by-step solution (Learning Curve):

1. Learning curve formula: T_n = T_1 × n^-0.322
where exponent = log(0.8)/log(2) = -0.322

2. Calculate cumulative time using integration:
Cumulative time for N units = T_1 × N^0.6780719051126377 / (learning_exponent + 1)

3. Time per batch:
Batch 1 (10 units): 47.1 minutes
Batch 2 (20 units): 26.0 minutes
Batch 3 (40 units): 19.2 minutes

4. Total time: 92.4 ≈ 92 minutes

Key Strategy: Learning curve reduces time with repetition; use cumulative average method for batch calculations.
Previous Worksheet Next Worksheet