Question 1
A job shop has 3 machines. Jobs and their routes:
- Job A: M3 → M2 → M1 with times 16, 19, 40
- Job B: M3 → M2 → M1 with times 26, 25, 17
- Job C: M2 → M3 → M1 with times 14, 30, 14
What is a lower bound on the minimum makespan?
Step-by-step solution:
1. Machine load bound: 72
2. Job processing bound: 75
3. Lower bound: 75
Answer: 75
1. Machine load bound: 72
2. Job processing bound: 75
3. Lower bound: 75
Answer: 75