Question 1
A job shop has 3 machines. Jobs and their routes:
- Job A: M3 → M2 → M1 with times 34, 37, 22
- Job B: M2 → M3 → M1 with times 11, 38, 36
- Job C: M2 → M3 → M1 with times 38, 29, 39
What is a lower bound on the minimum makespan?
Step-by-step solution:
1. Machine load bound: 101
2. Job processing bound: 106
3. Lower bound: 106
Answer: 106
1. Machine load bound: 101
2. Job processing bound: 106
3. Lower bound: 106
Answer: 106