Question 1
A job shop has 3 machines. Jobs and their routes:
- Job A: M2 → M3 → M1 with times 18, 20, 12
- Job B: M1 → M3 → M2 with times 31, 30, 26
- Job C: M3 → M1 → M2 with times 30, 29, 14
What is a lower bound on the minimum makespan?
Step-by-step solution:
1. Machine load bound: 80
2. Job processing bound: 87
3. Lower bound: 87
Answer: 87
1. Machine load bound: 80
2. Job processing bound: 87
3. Lower bound: 87
Answer: 87