Master JIT Penalty Scheduling - Intermediate-Advanced Level Problems JIT Penalty Scheduling INTERMEDIATE ADVANCED

Excel in competitive exams with this self assessment worksheet on JIT Penalty Scheduling. Worksheet 7 of 10 contains 20 intermediate-advanced-level problems. Target your accuracy improvement skills while practicing jit penalty scheduling shortcut methods, jit penalty scheduling bank exam questions, and jit penalty scheduling ssc cgl.

📝 Worksheet 7 of 10 • 20 questions • ⏱️ Estimated time: 20 minutes • 🎯 Intermediate Advanced level

What you'll learn in this worksheet:
Your progress through JIT Penalty Scheduling
Worksheet 7 of 10 (66% complete)

Question 1

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component D | 43 | 57 | 5 | 15 | | Component A | 60 | 139 | 3 | 12 | | Component C | 51 | 81 | 2 | 18 | | Component B | 26 | 80 | 5 | 16 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component D → Component B → Component C → Component A
2. Calculate completion times and penalties:
- Component D: completes at 43, due 57, early by 14 min → penalty 70
- Component B: completes at 69, due 80, early by 11 min → penalty 55
- Component C: completes at 120, due 81, late by 39 min → penalty 702
- Component A: completes at 180, due 139, late by 41 min → penalty 492

3. Total penalty: 1319

Answer: 1319 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 2

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component B | 37 | 50 | 5 | 10 | | Component A | 47 | 67 | 2 | 12 | | Component D | 57 | 72 | 5 | 20 | | Component C | 39 | 81 | 4 | 13 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component B → Component A → Component D → Component C
2. Calculate completion times and penalties:
- Component B: completes at 37, due 50, early by 13 min → penalty 65
- Component A: completes at 84, due 67, late by 17 min → penalty 204
- Component D: completes at 141, due 72, late by 69 min → penalty 1380
- Component C: completes at 180, due 81, late by 99 min → penalty 1287

3. Total penalty: 2936

Answer: 2936 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 3

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component B | 38 | 65 | 2 | 12 | | Component D | 23 | 55 | 1 | 16 | | Component A | 48 | 91 | 1 | 16 | | Component C | 39 | 96 | 5 | 13 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component D → Component B → Component A → Component C
2. Calculate completion times and penalties:
- Component D: completes at 23, due 55, early by 32 min → penalty 32
- Component B: completes at 61, due 65, early by 4 min → penalty 8
- Component A: completes at 109, due 91, late by 18 min → penalty 288
- Component C: completes at 148, due 96, late by 52 min → penalty 676

3. Total penalty: 1004

Answer: 1004 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 4

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component D | 25 | 92 | 4 | 20 | | Component C | 52 | 77 | 1 | 14 | | Component A | 39 | 93 | 2 | 15 | | Component B | 60 | 90 | 5 | 16 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component C → Component B → Component D → Component A
2. Calculate completion times and penalties:
- Component C: completes at 52, due 77, early by 25 min → penalty 25
- Component B: completes at 112, due 90, late by 22 min → penalty 352
- Component D: completes at 137, due 92, late by 45 min → penalty 900
- Component A: completes at 176, due 93, late by 83 min → penalty 1245

3. Total penalty: 2522

Answer: 2522 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 5

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component A | 52 | 75 | 1 | 11 | | Component C | 21 | 43 | 1 | 13 | | Component B | 36 | 87 | 2 | 14 | | Component D | 34 | 85 | 2 | 19 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component C → Component A → Component D → Component B
2. Calculate completion times and penalties:
- Component C: completes at 21, due 43, early by 22 min → penalty 22
- Component A: completes at 73, due 75, early by 2 min → penalty 2
- Component D: completes at 107, due 85, late by 22 min → penalty 418
- Component B: completes at 143, due 87, late by 56 min → penalty 784

3. Total penalty: 1226

Answer: 1226 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 6

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component A | 33 | 57 | 3 | 17 | | Component B | 20 | 93 | 4 | 14 | | Component D | 56 | 104 | 5 | 10 | | Component C | 40 | 91 | 2 | 13 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component A → Component C → Component B → Component D
2. Calculate completion times and penalties:
- Component A: completes at 33, due 57, early by 24 min → penalty 72
- Component C: completes at 73, due 91, early by 18 min → penalty 36
- Component B: completes exactly on time → penalty 0
- Component D: completes at 149, due 104, late by 45 min → penalty 450

3. Total penalty: 558

Answer: 558 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 7

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component C | 59 | 111 | 3 | 19 | | Component B | 43 | 53 | 5 | 11 | | Component D | 22 | 84 | 1 | 15 | | Component A | 24 | 65 | 5 | 17 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component B → Component A → Component D → Component C
2. Calculate completion times and penalties:
- Component B: completes at 43, due 53, early by 10 min → penalty 50
- Component A: completes at 67, due 65, late by 2 min → penalty 34
- Component D: completes at 89, due 84, late by 5 min → penalty 75
- Component C: completes at 148, due 111, late by 37 min → penalty 703

3. Total penalty: 862

Answer: 862 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 8

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component B | 38 | 69 | 5 | 16 | | Component D | 40 | 51 | 1 | 12 | | Component A | 51 | 70 | 4 | 16 | | Component C | 33 | 52 | 5 | 17 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component D → Component C → Component B → Component A
2. Calculate completion times and penalties:
- Component D: completes at 40, due 51, early by 11 min → penalty 11
- Component C: completes at 73, due 52, late by 21 min → penalty 357
- Component B: completes at 111, due 69, late by 42 min → penalty 672
- Component A: completes at 162, due 70, late by 92 min → penalty 1472

3. Total penalty: 2512

Answer: 2512 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 9

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component D | 44 | 93 | 4 | 14 | | Component A | 49 | 124 | 3 | 20 | | Component C | 22 | 61 | 1 | 13 | | Component B | 24 | 73 | 4 | 10 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component C → Component B → Component D → Component A
2. Calculate completion times and penalties:
- Component C: completes at 22, due 61, early by 39 min → penalty 39
- Component B: completes at 46, due 73, early by 27 min → penalty 108
- Component D: completes at 90, due 93, early by 3 min → penalty 12
- Component A: completes at 139, due 124, late by 15 min → penalty 300

3. Total penalty: 459

Answer: 459 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 10

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component A | 53 | 100 | 5 | 15 | | Component D | 38 | 82 | 3 | 10 | | Component C | 32 | 92 | 4 | 15 | | Component B | 24 | 77 | 1 | 20 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component B → Component D → Component C → Component A
2. Calculate completion times and penalties:
- Component B: completes at 24, due 77, early by 53 min → penalty 53
- Component D: completes at 62, due 82, early by 20 min → penalty 60
- Component C: completes at 94, due 92, late by 2 min → penalty 30
- Component A: completes at 147, due 100, late by 47 min → penalty 705

3. Total penalty: 848

Answer: 848 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 11

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component C | 35 | 93 | 4 | 11 | | Component A | 35 | 96 | 1 | 11 | | Component D | 47 | 105 | 1 | 14 | | Component B | 31 | 82 | 5 | 13 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component B → Component C → Component A → Component D
2. Calculate completion times and penalties:
- Component B: completes at 31, due 82, early by 51 min → penalty 255
- Component C: completes at 66, due 93, early by 27 min → penalty 108
- Component A: completes at 101, due 96, late by 5 min → penalty 55
- Component D: completes at 148, due 105, late by 43 min → penalty 602

3. Total penalty: 1020

Answer: 1020 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 12

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component B | 52 | 75 | 4 | 18 | | Component C | 48 | 88 | 5 | 20 | | Component D | 30 | 71 | 4 | 11 | | Component A | 29 | 86 | 5 | 13 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component D → Component B → Component A → Component C
2. Calculate completion times and penalties:
- Component D: completes at 30, due 71, early by 41 min → penalty 164
- Component B: completes at 82, due 75, late by 7 min → penalty 126
- Component A: completes at 111, due 86, late by 25 min → penalty 325
- Component C: completes at 159, due 88, late by 71 min → penalty 1420

3. Total penalty: 2035

Answer: 2035 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 13

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component A | 35 | 48 | 4 | 14 | | Component D | 30 | 57 | 2 | 16 | | Component B | 57 | 87 | 5 | 11 | | Component C | 47 | 126 | 2 | 13 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component A → Component D → Component B → Component C
2. Calculate completion times and penalties:
- Component A: completes at 35, due 48, early by 13 min → penalty 52
- Component D: completes at 65, due 57, late by 8 min → penalty 128
- Component B: completes at 122, due 87, late by 35 min → penalty 385
- Component C: completes at 169, due 126, late by 43 min → penalty 559

3. Total penalty: 1124

Answer: 1124 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 14

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component C | 49 | 114 | 3 | 17 | | Component B | 20 | 51 | 1 | 20 | | Component D | 42 | 96 | 5 | 14 | | Component A | 52 | 79 | 4 | 10 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component B → Component A → Component D → Component C
2. Calculate completion times and penalties:
- Component B: completes at 20, due 51, early by 31 min → penalty 31
- Component A: completes at 72, due 79, early by 7 min → penalty 28
- Component D: completes at 114, due 96, late by 18 min → penalty 252
- Component C: completes at 163, due 114, late by 49 min → penalty 833

3. Total penalty: 1144

Answer: 1144 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 15

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component D | 36 | 112 | 4 | 14 | | Component A | 51 | 106 | 3 | 18 | | Component B | 20 | 69 | 1 | 13 | | Component C | 56 | 69 | 4 | 11 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component B → Component C → Component A → Component D
2. Calculate completion times and penalties:
- Component B: completes at 20, due 69, early by 49 min → penalty 49
- Component C: completes at 76, due 69, late by 7 min → penalty 77
- Component A: completes at 127, due 106, late by 21 min → penalty 378
- Component D: completes at 163, due 112, late by 51 min → penalty 714

3. Total penalty: 1218

Answer: 1218 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 16

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component D | 54 | 112 | 1 | 11 | | Component A | 43 | 123 | 1 | 19 | | Component B | 32 | 83 | 4 | 10 | | Component C | 20 | 49 | 3 | 19 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component C → Component B → Component D → Component A
2. Calculate completion times and penalties:
- Component C: completes at 20, due 49, early by 29 min → penalty 87
- Component B: completes at 52, due 83, early by 31 min → penalty 124
- Component D: completes at 106, due 112, early by 6 min → penalty 6
- Component A: completes at 149, due 123, late by 26 min → penalty 494

3. Total penalty: 711

Answer: 711 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 17

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component B | 23 | 58 | 1 | 15 | | Component D | 31 | 74 | 3 | 11 | | Component C | 40 | 84 | 2 | 16 | | Component A | 44 | 58 | 5 | 11 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component B → Component A → Component D → Component C
2. Calculate completion times and penalties:
- Component B: completes at 23, due 58, early by 35 min → penalty 35
- Component A: completes at 67, due 58, late by 9 min → penalty 99
- Component D: completes at 98, due 74, late by 24 min → penalty 264
- Component C: completes at 138, due 84, late by 54 min → penalty 864

3. Total penalty: 1262

Answer: 1262 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 18

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component D | 48 | 125 | 1 | 20 | | Component B | 32 | 107 | 2 | 20 | | Component A | 57 | 114 | 1 | 17 | | Component C | 38 | 89 | 2 | 11 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component C → Component B → Component A → Component D
2. Calculate completion times and penalties:
- Component C: completes at 38, due 89, early by 51 min → penalty 102
- Component B: completes at 70, due 107, early by 37 min → penalty 74
- Component A: completes at 127, due 114, late by 13 min → penalty 221
- Component D: completes at 175, due 125, late by 50 min → penalty 1000

3. Total penalty: 1397

Answer: 1397 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 19

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component B | 35 | 92 | 1 | 11 | | Component D | 42 | 85 | 5 | 13 | | Component A | 34 | 80 | 5 | 13 | | Component C | 58 | 114 | 5 | 10 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component A → Component D → Component B → Component C
2. Calculate completion times and penalties:
- Component A: completes at 34, due 80, early by 46 min → penalty 230
- Component D: completes at 76, due 85, early by 9 min → penalty 45
- Component B: completes at 111, due 92, late by 19 min → penalty 209
- Component C: completes at 169, due 114, late by 55 min → penalty 550

3. Total penalty: 1034

Answer: 1034 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 20

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component C | 57 | 135 | 2 | 15 | | Component A | 38 | 76 | 1 | 16 | | Component B | 52 | 74 | 5 | 14 | | Component D | 34 | 65 | 3 | 11 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component D → Component B → Component A → Component C
2. Calculate completion times and penalties:
- Component D: completes at 34, due 65, early by 31 min → penalty 93
- Component B: completes at 86, due 74, late by 12 min → penalty 168
- Component A: completes at 124, due 76, late by 48 min → penalty 768
- Component C: completes at 181, due 135, late by 46 min → penalty 690

3. Total penalty: 1719

Answer: 1719 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.
Previous Worksheet Next Worksheet