JIT Penalty Scheduling Beginner-Intermediate Worksheet: Focus on common variations practice JIT Penalty Scheduling BEGINNER INTERMEDIATE

Level up your JIT Penalty Scheduling skills! You're at Worksheet 4 of 10 (33% through this series). This step-up challenge worksheet features 20 beginner-intermediate-level problems with a focus on common variations practice. Topics covered: jit penalty scheduling for competitive exams, how to solve jit penalty scheduling, jit penalty scheduling tricks.

📝 Worksheet 4 of 10 • 20 questions • ⏱️ Estimated time: 20 minutes • 🎯 Beginner Intermediate level

What you'll learn in this worksheet:
Your progress through JIT Penalty Scheduling
Worksheet 4 of 10 (33% complete)

Question 1

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component D | 38 | 83 | 3 | 10 | | Component A | 23 | 77 | 1 | 16 | | Component B | 59 | 121 | 5 | 20 | | Component C | 31 | 66 | 3 | 14 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component C → Component A → Component D → Component B
2. Calculate completion times and penalties:
- Component C: completes at 31, due 66, early by 35 min → penalty 105
- Component A: completes at 54, due 77, early by 23 min → penalty 23
- Component D: completes at 92, due 83, late by 9 min → penalty 90
- Component B: completes at 151, due 121, late by 30 min → penalty 600

3. Total penalty: 818

Answer: 818 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 2

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component D | 55 | 80 | 3 | 18 | | Component B | 44 | 63 | 2 | 19 | | Component C | 29 | 47 | 5 | 10 | | Component A | 29 | 46 | 1 | 10 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component A → Component C → Component B → Component D
2. Calculate completion times and penalties:
- Component A: completes at 29, due 46, early by 17 min → penalty 17
- Component C: completes at 58, due 47, late by 11 min → penalty 110
- Component B: completes at 102, due 63, late by 39 min → penalty 741
- Component D: completes at 157, due 80, late by 77 min → penalty 1386

3. Total penalty: 2254

Answer: 2254 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 3

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component B | 33 | 48 | 1 | 17 | | Component D | 31 | 104 | 5 | 16 | | Component C | 21 | 41 | 3 | 18 | | Component A | 20 | 73 | 2 | 12 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component C → Component B → Component A → Component D
2. Calculate completion times and penalties:
- Component C: completes at 21, due 41, early by 20 min → penalty 60
- Component B: completes at 54, due 48, late by 6 min → penalty 102
- Component A: completes at 74, due 73, late by 1 min → penalty 12
- Component D: completes at 105, due 104, late by 1 min → penalty 16

3. Total penalty: 190

Answer: 190 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 4

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component A | 41 | 87 | 4 | 10 | | Component B | 57 | 134 | 3 | 12 | | Component D | 32 | 74 | 3 | 20 | | Component C | 30 | 92 | 1 | 17 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component D → Component A → Component C → Component B
2. Calculate completion times and penalties:
- Component D: completes at 32, due 74, early by 42 min → penalty 126
- Component A: completes at 73, due 87, early by 14 min → penalty 56
- Component C: completes at 103, due 92, late by 11 min → penalty 187
- Component B: completes at 160, due 134, late by 26 min → penalty 312

3. Total penalty: 681

Answer: 681 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 5

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component C | 22 | 56 | 5 | 18 | | Component D | 22 | 101 | 2 | 15 | | Component B | 49 | 126 | 4 | 19 | | Component A | 30 | 66 | 3 | 14 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component C → Component A → Component D → Component B
2. Calculate completion times and penalties:
- Component C: completes at 22, due 56, early by 34 min → penalty 170
- Component A: completes at 52, due 66, early by 14 min → penalty 42
- Component D: completes at 74, due 101, early by 27 min → penalty 54
- Component B: completes at 123, due 126, early by 3 min → penalty 12

3. Total penalty: 278

Answer: 278 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 6

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component D | 51 | 93 | 1 | 15 | | Component C | 23 | 53 | 3 | 19 | | Component A | 26 | 42 | 5 | 15 | | Component B | 41 | 87 | 3 | 13 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component A → Component C → Component B → Component D
2. Calculate completion times and penalties:
- Component A: completes at 26, due 42, early by 16 min → penalty 80
- Component C: completes at 49, due 53, early by 4 min → penalty 12
- Component B: completes at 90, due 87, late by 3 min → penalty 39
- Component D: completes at 141, due 93, late by 48 min → penalty 720

3. Total penalty: 851

Answer: 851 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 7

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component D | 55 | 117 | 3 | 13 | | Component C | 58 | 69 | 5 | 20 | | Component A | 60 | 128 | 4 | 20 | | Component B | 31 | 94 | 5 | 14 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component C → Component B → Component D → Component A
2. Calculate completion times and penalties:
- Component C: completes at 58, due 69, early by 11 min → penalty 55
- Component B: completes at 89, due 94, early by 5 min → penalty 25
- Component D: completes at 144, due 117, late by 27 min → penalty 351
- Component A: completes at 204, due 128, late by 76 min → penalty 1520

3. Total penalty: 1951

Answer: 1951 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 8

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component C | 54 | 79 | 3 | 18 | | Component D | 53 | 86 | 2 | 19 | | Component A | 51 | 87 | 3 | 10 | | Component B | 44 | 96 | 5 | 10 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component C → Component D → Component A → Component B
2. Calculate completion times and penalties:
- Component C: completes at 54, due 79, early by 25 min → penalty 75
- Component D: completes at 107, due 86, late by 21 min → penalty 399
- Component A: completes at 158, due 87, late by 71 min → penalty 710
- Component B: completes at 202, due 96, late by 106 min → penalty 1060

3. Total penalty: 2244

Answer: 2244 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 9

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component C | 41 | 114 | 4 | 15 | | Component D | 42 | 60 | 5 | 14 | | Component A | 26 | 39 | 3 | 16 | | Component B | 50 | 88 | 5 | 18 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component A → Component D → Component B → Component C
2. Calculate completion times and penalties:
- Component A: completes at 26, due 39, early by 13 min → penalty 39
- Component D: completes at 68, due 60, late by 8 min → penalty 112
- Component B: completes at 118, due 88, late by 30 min → penalty 540
- Component C: completes at 159, due 114, late by 45 min → penalty 675

3. Total penalty: 1366

Answer: 1366 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 10

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component B | 57 | 102 | 5 | 11 | | Component D | 31 | 107 | 1 | 20 | | Component C | 24 | 84 | 1 | 12 | | Component A | 28 | 87 | 2 | 13 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component C → Component A → Component B → Component D
2. Calculate completion times and penalties:
- Component C: completes at 24, due 84, early by 60 min → penalty 60
- Component A: completes at 52, due 87, early by 35 min → penalty 70
- Component B: completes at 109, due 102, late by 7 min → penalty 77
- Component D: completes at 140, due 107, late by 33 min → penalty 660

3. Total penalty: 867

Answer: 867 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 11

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component D | 33 | 75 | 1 | 18 | | Component C | 33 | 113 | 3 | 13 | | Component B | 27 | 60 | 2 | 16 | | Component A | 22 | 56 | 1 | 15 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component A → Component B → Component D → Component C
2. Calculate completion times and penalties:
- Component A: completes at 22, due 56, early by 34 min → penalty 34
- Component B: completes at 49, due 60, early by 11 min → penalty 22
- Component D: completes at 82, due 75, late by 7 min → penalty 126
- Component C: completes at 115, due 113, late by 2 min → penalty 26

3. Total penalty: 208

Answer: 208 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 12

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component B | 38 | 110 | 2 | 20 | | Component C | 42 | 99 | 3 | 12 | | Component A | 50 | 93 | 3 | 12 | | Component D | 24 | 95 | 1 | 12 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component A → Component D → Component C → Component B
2. Calculate completion times and penalties:
- Component A: completes at 50, due 93, early by 43 min → penalty 129
- Component D: completes at 74, due 95, early by 21 min → penalty 21
- Component C: completes at 116, due 99, late by 17 min → penalty 204
- Component B: completes at 154, due 110, late by 44 min → penalty 880

3. Total penalty: 1234

Answer: 1234 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 13

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component A | 21 | 77 | 4 | 11 | | Component C | 34 | 110 | 3 | 15 | | Component D | 46 | 90 | 2 | 13 | | Component B | 25 | 63 | 1 | 11 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component B → Component A → Component D → Component C
2. Calculate completion times and penalties:
- Component B: completes at 25, due 63, early by 38 min → penalty 38
- Component A: completes at 46, due 77, early by 31 min → penalty 124
- Component D: completes at 92, due 90, late by 2 min → penalty 26
- Component C: completes at 126, due 110, late by 16 min → penalty 240

3. Total penalty: 428

Answer: 428 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 14

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component D | 32 | 66 | 5 | 14 | | Component C | 24 | 36 | 5 | 13 | | Component B | 55 | 73 | 4 | 10 | | Component A | 58 | 128 | 4 | 19 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component C → Component D → Component B → Component A
2. Calculate completion times and penalties:
- Component C: completes at 24, due 36, early by 12 min → penalty 60
- Component D: completes at 56, due 66, early by 10 min → penalty 50
- Component B: completes at 111, due 73, late by 38 min → penalty 380
- Component A: completes at 169, due 128, late by 41 min → penalty 779

3. Total penalty: 1269

Answer: 1269 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 15

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component B | 24 | 78 | 3 | 16 | | Component D | 38 | 62 | 3 | 15 | | Component A | 33 | 113 | 5 | 19 | | Component C | 26 | 61 | 3 | 18 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component C → Component D → Component B → Component A
2. Calculate completion times and penalties:
- Component C: completes at 26, due 61, early by 35 min → penalty 105
- Component D: completes at 64, due 62, late by 2 min → penalty 30
- Component B: completes at 88, due 78, late by 10 min → penalty 160
- Component A: completes at 121, due 113, late by 8 min → penalty 152

3. Total penalty: 447

Answer: 447 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 16

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component C | 52 | 73 | 5 | 17 | | Component B | 21 | 64 | 3 | 18 | | Component D | 33 | 49 | 3 | 17 | | Component A | 31 | 49 | 4 | 17 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component D → Component A → Component B → Component C
2. Calculate completion times and penalties:
- Component D: completes at 33, due 49, early by 16 min → penalty 48
- Component A: completes at 64, due 49, late by 15 min → penalty 255
- Component B: completes at 85, due 64, late by 21 min → penalty 378
- Component C: completes at 137, due 73, late by 64 min → penalty 1088

3. Total penalty: 1769

Answer: 1769 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 17

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component C | 55 | 75 | 4 | 20 | | Component D | 46 | 91 | 4 | 18 | | Component B | 35 | 109 | 1 | 15 | | Component A | 56 | 85 | 4 | 16 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component C → Component A → Component D → Component B
2. Calculate completion times and penalties:
- Component C: completes at 55, due 75, early by 20 min → penalty 80
- Component A: completes at 111, due 85, late by 26 min → penalty 416
- Component D: completes at 157, due 91, late by 66 min → penalty 1188
- Component B: completes at 192, due 109, late by 83 min → penalty 1245

3. Total penalty: 2929

Answer: 2929 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 18

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component A | 47 | 123 | 5 | 14 | | Component B | 35 | 53 | 3 | 16 | | Component C | 32 | 99 | 2 | 14 | | Component D | 38 | 64 | 1 | 14 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component B → Component D → Component C → Component A
2. Calculate completion times and penalties:
- Component B: completes at 35, due 53, early by 18 min → penalty 54
- Component D: completes at 73, due 64, late by 9 min → penalty 126
- Component C: completes at 105, due 99, late by 6 min → penalty 84
- Component A: completes at 152, due 123, late by 29 min → penalty 406

3. Total penalty: 670

Answer: 670 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 19

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component B | 32 | 63 | 5 | 10 | | Component A | 34 | 56 | 2 | 10 | | Component D | 29 | 105 | 4 | 12 | | Component C | 43 | 105 | 4 | 15 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component A → Component B → Component D → Component C
2. Calculate completion times and penalties:
- Component A: completes at 34, due 56, early by 22 min → penalty 44
- Component B: completes at 66, due 63, late by 3 min → penalty 30
- Component D: completes at 95, due 105, early by 10 min → penalty 40
- Component C: completes at 138, due 105, late by 33 min → penalty 495

3. Total penalty: 609

Answer: 609 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.

Question 20

A JIT manufacturing system has 4 jobs with the following data: | Job | Processing (min) | Due Date (min) | Early Penalty/min | Late Penalty/min | |-----|-----------------|----------------|-------------------|------------------| | Component D | 59 | 112 | 4 | 16 | | Component C | 54 | 71 | 4 | 16 | | Component A | 33 | 87 | 3 | 11 | | Component B | 25 | 98 | 4 | 20 | Using the Earliest Due Date (EDD) sequencing rule, what is the total penalty incurred?
Step-by-step solution (JIT Penalty Calculation):

1. EDD Sequence: Component C → Component A → Component B → Component D
2. Calculate completion times and penalties:
- Component C: completes at 54, due 71, early by 17 min → penalty 68
- Component A: completes exactly on time → penalty 0
- Component B: completes at 112, due 98, late by 14 min → penalty 280
- Component D: completes at 171, due 112, late by 59 min → penalty 944

3. Total penalty: 1292

Answer: 1292 penalty points

Key Strategy: JIT scheduling minimizes total earliness + tardiness penalties, balancing inventory costs and customer satisfaction.
Previous Worksheet Next Worksheet