Question 1
A flow shop has 2 machines (M1 → M2). Jobs and processing times (M1, M2):
- Job A: (13, 32)
- Job B: (12, 46)
- Job C: (43, 50)
- Job D: (44, 26)
- Job E: (15, 45)
- Job F: (16, 24)
Using Johnson's Rule, what is the minimum makespan?
Step-by-step solution (Johnson's Rule):
1. Apply Johnson's Rule:
- If M1 time < M2 time, schedule early
- If M2 time < M1 time, schedule late
2. Optimal sequence: Job D → Job B → Job A → Job E → Job F → Job C
3. Calculate makespan: 267
Answer: 267
1. Apply Johnson's Rule:
- If M1 time < M2 time, schedule early
- If M2 time < M1 time, schedule late
2. Optimal sequence: Job D → Job B → Job A → Job E → Job F → Job C
3. Calculate makespan: 267
Answer: 267