Question 1
A flow shop has 2 machines (M1 → M2). Jobs and processing times (M1, M2):
- Job A: (20, 28)
- Job B: (19, 35)
- Job C: (19, 12)
- Job D: (42, 18)
- Job E: (20, 43)
Using Johnson's Rule, what is the minimum makespan?
Step-by-step solution (Johnson's Rule):
1. Apply Johnson's Rule:
- If M1 time < M2 time, schedule early
- If M2 time < M1 time, schedule late
2. Optimal sequence: Job D → Job C → Job B → Job A → Job E
3. Calculate makespan: 186
Answer: 186
1. Apply Johnson's Rule:
- If M1 time < M2 time, schedule early
- If M2 time < M1 time, schedule late
2. Optimal sequence: Job D → Job C → Job B → Job A → Job E
3. Calculate makespan: 186
Answer: 186