Question 1
A flow shop has 2 machines (M1 → M2). Jobs and processing times (M1, M2):
- Job A: (11, 47)
- Job B: (30, 26)
- Job C: (25, 46)
- Job D: (19, 10)
- Job E: (45, 39)
- Job F: (28, 10)
Using Johnson's Rule, what is the minimum makespan?
Step-by-step solution (Johnson's Rule):
1. Apply Johnson's Rule:
- If M1 time < M2 time, schedule early
- If M2 time < M1 time, schedule late
2. Optimal sequence: Job E → Job B → Job F → Job D → Job A → Job C
3. Calculate makespan: 226
Answer: 226
1. Apply Johnson's Rule:
- If M1 time < M2 time, schedule early
- If M2 time < M1 time, schedule late
2. Optimal sequence: Job E → Job B → Job F → Job D → Job A → Job C
3. Calculate makespan: 226
Answer: 226