Work and Time - Intermediate Level: tricky scenarios handling
Work and TimeINTERMEDIATE
This expert challenge 📈 worksheet focuses on Work and Time - a key topic in Data Sufficiency. You'll solve 20 intermediate-level problems (Worksheet 5 of 10). The primary focus is on tricky scenarios handling. Master how to solve work and time, work and time tricks, and work and time shortcut methods through systematic practice.
Master how to solve work and time through focused practice
Understand the logic behind work and time tricks
Learn step-by-step approaches to tricky scenarios handling
Improve your solving speed while maintaining accuracy
Learn to eliminate wrong options efficiently
Your progress through Work and Time
Worksheet 5 of 10 (44% complete)
Question 1
Question: How many days will A take to complete the work alone?
Statement (1): A and B together complete the work in 6 days.
Statement (2): B alone completes the work in 10 days.
Work equation: 1/A + 1/B = 1/6, B = 10 → 1/A = 1/6 - 1/10 = (5-3)/30 = 2/30 = 1/15 → A = 15 days.
Question 2
Question: How many days will B take to complete the work alone?
Statement (1): A and B together complete the work in 12 days.
Statement (2): A alone completes the work in 20 days.
Question: How many days will A take to complete the work alone?
Statement (1): A and B together complete the work in 6 days.
Statement (2): B alone completes the work in 10 days.
Work equation: 1/A + 1/B = 1/6, B = 10 → 1/A = 1/6 - 1/10 = (5-3)/30 = 2/30 = 1/15 → A = 15 days.
Question 4
Question: How many days will B take to complete the work alone?
Statement (1): A and B together complete the work in 12 days.
Statement (2): A alone completes the work in 20 days.
Question: How many days will B take to complete the work alone?
Statement (1): A and B together complete the work in 12 days.
Statement (2): A alone completes the work in 20 days.
Question: How many days will B take to complete the work alone?
Statement (1): A and B together complete the work in 12 days.
Statement (2): A alone completes the work in 20 days.
Question: How many days will B take to complete the work alone?
Statement (1): A and B together complete the work in 12 days.
Statement (2): A alone completes the work in 20 days.
Question: How many days will B take to complete the work alone?
Statement (1): A and B together complete the work in 12 days.
Statement (2): A alone completes the work in 20 days.
Question: How many days will B take to complete the work alone?
Statement (1): A and B together complete the work in 12 days.
Statement (2): A alone completes the work in 20 days.
Question: How many days will A take to complete the work alone?
Statement (1): A and B together complete the work in 6 days.
Statement (2): B alone completes the work in 10 days.
Work equation: 1/A + 1/B = 1/6, B = 10 → 1/A = 1/6 - 1/10 = (5-3)/30 = 2/30 = 1/15 → A = 15 days.
Question 11
Question: How many days will B take to complete the work alone?
Statement (1): A and B together complete the work in 12 days.
Statement (2): A alone completes the work in 20 days.
Question: How many days will B take to complete the work alone?
Statement (1): A and B together complete the work in 12 days.
Statement (2): A alone completes the work in 20 days.
Question: How many days will B take to complete the work alone?
Statement (1): A and B together complete the work in 12 days.
Statement (2): A alone completes the work in 20 days.
Question: How many days will A take to complete the work alone?
Statement (1): A and B together complete the work in 6 days.
Statement (2): B alone completes the work in 10 days.
Work equation: 1/A + 1/B = 1/6, B = 10 → 1/A = 1/6 - 1/10 = (5-3)/30 = 2/30 = 1/15 → A = 15 days.
Question 15
Question: How many days will B take to complete the work alone?
Statement (1): A and B together complete the work in 12 days.
Statement (2): A alone completes the work in 20 days.
Question: How many days will A take to complete the work alone?
Statement (1): A and B together complete the work in 6 days.
Statement (2): B alone completes the work in 10 days.
Work equation: 1/A + 1/B = 1/6, B = 10 → 1/A = 1/6 - 1/10 = (5-3)/30 = 2/30 = 1/15 → A = 15 days.
Question 17
Question: How many days will B take to complete the work alone?
Statement (1): A and B together complete the work in 12 days.
Statement (2): A alone completes the work in 20 days.
Question: How many days will A take to complete the work alone?
Statement (1): A and B together complete the work in 6 days.
Statement (2): B alone completes the work in 10 days.
Work equation: 1/A + 1/B = 1/6, B = 10 → 1/A = 1/6 - 1/10 = (5-3)/30 = 2/30 = 1/15 → A = 15 days.
Question 19
Question: How many days will A take to complete the work alone?
Statement (1): A and B together complete the work in 6 days.
Statement (2): B alone completes the work in 10 days.
Work equation: 1/A + 1/B = 1/6, B = 10 → 1/A = 1/6 - 1/10 = (5-3)/30 = 2/30 = 1/15 → A = 15 days.
Question 20
Question: How many days will A take to complete the work alone?
Statement (1): A and B together complete the work in 6 days.
Statement (2): B alone completes the work in 10 days.
Work equation: 1/A + 1/B = 1/6, B = 10 → 1/A = 1/6 - 1/10 = (5-3)/30 = 2/30 = 1/15 → A = 15 days.